The Mayor and Cabinet of Lewisham decided to approve the award of the Lewisham Library Operator concession contract to Blue Garage Ltd for a period of five years, with an option to extend for up to a further five years, at a value of £10,704,000. They also approved variations to contracts with Rooff Construction Ltd and Architecture 00, and agreed contingency provisions. Authority was delegated to the Executive Director for Place to enter into contract and lease documentation, exercise extension options, and agree final terms for contract variations.
Full council record
Decision
Resolved- That Mayor & Cabinet:
1) Note the overarching progress on the Lewisham Town Centre Improvement Programme
2) Approve the award of the Lewisham Library Operator concession contract to Blue Garage Ltd for a period of five years with the option to extend for up to a further 5 years at a value of £10,704,000 over the full contract period.
3) Delegate authority to the Executive Director for Place, in consultation with the Director of Law and Corporate Governance, to enter into the contract and lease documentation and exercise any extension options
4) Approve a variation up to the amount set out in Part 2 to the contract with Rooff Construction Ltd, originally awarded at £6,532,085, to meet the identified additional works, risk pricing and programme prolongation costs arising through delivery of the Lewisham Library refurbishment.
5) Approve a contingency provision as set out in Part 2, to be drawn down only where required through the Council’s contract change-control arrangements.
6) Approve a variation up to the amount set out in Part 2 to the contract with Architecture 00, originally awarded at £570,375, to meet the identified additional services, design requirements and programme prolongation costs associated with completion of the Lewisham Library refurbishment.
7) Approve a further contingency provision as set out in Part 2, to be drawn down only where required through the Council’s contract change-control arrangements.
8) Delegate authority to the Executive Director for Place, in consultation with the Director of Law and Corporate Governance, to agree the final terms of these variations within the maximum values approved above.
Related Meeting
Mayor and Cabinet - Wednesday, 7th October, 2026 6.00 pm on October 7, 2026
Supporting Documents
Details
| Reference | Call-ins0 |
| Outcome | Recommendations Approved |
| Decision date | 7 Oct 2026 |
| Effective from | 17 Oct 2026 |
| Expected date | 7 Oct 2026 |
| Originally due | 9 Sep 2026 |
| Lead officer | Spike van der Vliet-Firth |