Nettleham Road Roundabout Scheme
June 19, 2026 Executive Councillor: Highways & Transport, Executive Councillor: Resources (Other) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Executive Councillor: Children's Services approved the council's special schools funding formula proposals for 2026/27 on 16/06/2026. The decision approved the proposals as set out in Appendix A to the report.
Executive Councillor for Resources and Executive Councillor for Highways and Transport approved the Nettleham Road Roundabout scheme on 15-19 June 2026. The decision authorised pursuing land acquisition, submitting a planning application, and awarding the construction contract.
The Greater Lincolnshire Combined County Authority approved the approach to performance management and interim performance reporting arrangements for financial year 26/27 on 24 June 2026. The Authority noted that a full outcomes framework approach will continue to be developed for reporting in 27/28.
Full council record
Decision
Decision by the Executive Councillor for Resources:
That the Nettleham Road Roundabout project (Scheme), as detailed in the report, be approved.
Decision by the Executive Councillor for Highways and Transport:
- That the submission of the planning application for the Scheme be approved.
- That, subject to planning permission being granted, the Chief Legal Officer be authorised to acquire for planning purposes, pursuant to Section 227 of the Town and Country Planning Act 1990, all third-party land and interests required to support the delivery of the Scheme by agreement.
- That the undertaking of the procurement process for construction and delivery of the Scheme be approved, and that authority be delegated to the Executive Director, in consultation with the Executive Councillor for Highways and Transport, to take all decisions necessary to progress the Scheme up to and including the determination of the final form of contract and the award and execution of the contract and such other documentation necessary to deliver the Scheme.
Reasons for the decision
As detailed in the report
Alternative options considered
As detailed in the report
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 19 Jun 2026 |
| Lead officer | Sam Edwards |