Mansfield Crematorium Redevelopment (Key Decision)
April 1, 2025 Cabinet (Cabinet collective) Key decision Approved View on council websiteFull council record
Decision
That Cabinet
approve:
a)
Option C the high level refurbishment of Mansfield
Crematorium as detailed in Exempt Appendix A to the report, and
commencement of the refurbishment project;
b)
the allocation of the Usable Reserves to partially
cover the VAT liability on the development, limiting the financial
impact on each authority area for the refurbishment programme, as
set out in Annex A within Exempt Appendix A to the
report;
c)
the remaining total contribution by the Council, to
pay the remaining VAT liability and year one deficit, as set out in
paragraphs 2.45, 2.46 and Annex A within Exempt Appendix A to the
report; and
d)
an increase to the Capital Programme by
£211,900, funded by the Change Management Reserve, to fund
the Council’s contribution towards the high-level
refurbishment works as suggested in Option C.
Related Meeting
Cabinet - Tuesday, 1st April, 2025 6.00 pm on April 1, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 1 Apr 2025 |
| Subject to call-in | Yes |