Sherwood Avenue Park (Key Decision)

December 19, 2023 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to support the redevelopment of Sherwood Avenue Park, allocating funds and approving a budget of £520,400 for the project, and to proceed with a public consultation before formally tendering the scheme.

Full council record

Decision

AGREED that
Cabinet:
 

a)      
formally supports the development of the scheme as
set out in the report and appendices, and in line with the cost
plan;
 

b)      
agrees that Section 106 monies from the Arkwood
development on Lord Hawke Way are allocated to the
scheme;
 

c)       
approve the Capital Programme budget of
£520,400 financed by Section 106, Shared Prosperity Fund,
Capital Receipt and Newark Town Council Contribution;
 

d)      
supports a short period of public consultation in
the new year, to ensure the plans align with community feedback and
aspirations for the site; and
 

e)      
subject to no material changes being required from
the consultation exercise, the scheme and its packages are formally
tendered and the scheme is progressed through to
delivery.

Supporting Documents

19.12.23 - Sherwood Avenue Park Appendix 2.pdf
19.12.23 - Sherwood Avenue Park.pdf
19.12.23 - Sherwood Avenue Park Appendix 1.pdf
19.12.23 - Sherwood Avenue Park Appendix 3.pdf
19.12.23 - Sherwood Avenue Park Appendix 4.pdf
19.12.23 - Sherwood Avenue Park Appendix 5.pdf

Details

OutcomeRecommendations Approved
Decision date19 Dec 2023
Subject to call-inYes