Building a Fairer Newham Corporate Delivery Plan Review

February 18, 2025 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve revisions to the Corporate Delivery Plan and the revised Performance Framework, including updates to Key Performance Indicators, to better align with funding, feasibility, and the Council's strategic priorities for 2025/26.

Full council record

Purpose

The report proposes changes to the current
Building a Fairer Newham Delivery Plan and Performance framework
for 25/26. Cabinet is being asked to agree the proposals

Decision

Decision
 
For the reasons set out in the report and its
appendices Cabinet RESOLVED to Agree:
 

i) 
The revisions to the Corporate Delivery Plan, as detailed in
Appendix 1, which ensures alignment with funding availability,
feasibility, and a focus on delivering priority actions.

ii) 
The revised Performance Framework, as outlined in Appendix 2,
including updates to the BaFN Key
Performance Indicators (KPIs), to better support monitoring and
achievement of the Council’s strategic priorities.
 
Alternatives
Considered
 

a) 
An alternative would be to retain the Corporate Delivery Plan as
originally adopted in September 2022. However, this is not
recommended due to significant changes in the external and internal
context, including increased financial pressures, rising demand for
services such as Temporary Accommodation, and stretched
organisational capacity.

b) 
The LGA Corporate Peer Review highlighted the need to prioritise
and focus on short-, medium-, and long-term goals, making clear
decisions about what the Council can and cannot do. Reviewing the
Plan ensures alignment with current challenges and commitments,
enabling the Council to deliver the most value to residents within
its capacity.
 

Related Meeting

Cabinet - Tuesday 18th February 2025 10.30 a.m. on February 18, 2025

Supporting Documents

Building a Fairer Newham Corporate Delivery Plan review CABINET report 180224 - FINAL 003.pdf
Appendix 1 - Proposed changes to BaFN CDP - Priority_FINAL_100225 1.pdf
Appendix 2 - Proposed changes to BaFN set of KPIs - Priority_FINAL_100225.pdf

Details

OutcomeDecision approved
Decision date18 Feb 2025
Subject to call-inYes