Beckton Community Centre Refurbishment - Approval to Award Contract

July 6, 2023 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to award Olli Construction Ltd a £1,498,113 contract for the refurbishment of Beckton Community Centre, with work scheduled to begin in October 2023.

Full council record

Purpose

This report seeks approval to award a contract
to refurbish Beckton Community
Centre.  A tender process has been
completed and a successful contractor identified to deliver the
works. This report recommends that the contract should be awarded
to Olli Construction Ltd in the sum of £1,498,112.99 for the
refurbishment of Beckton Community
Centre.

Decision

For the reasons set out in
the report and its appendices Cabinet RESOLVED to AGREE:
 
i) 
The award of contract to Olli Construction Ltd in
the sum of £1,498,113million for the refurbishment of Beckton
Community Centre to start in October 2023.
 
Alternatives
Considered
 

1) 
Do Nothing - Not recommended.  The Centre would fall into disrepair, cost more to
refurbish in the future and ultimately may need to close for a
longer period until funding is secured and the works are
completed.
 

2) 
Different procurement route/cost and
quality split - Not recommended.  The
procurement route was discussed with the Strategic Procurement Team
who recommended the proposed procurement route to achieve
competitive bids and best value.
 
 
 

Supporting Documents

Final Beckton Community Centre Contract Award No LMI with PSED added 28.6.23 clean.pdf

Details

OutcomeDecision approved
Decision date6 Jul 2023
Subject to call-inYes