Pre Procurement Report Approval - Schools Capital Condition Programme 2026/2027

November 17, 2026 Cabinet (Cabinet collective) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Cabinet of Newham Council decided to accept £4,021,591 of grant funding from the Department for Education for the School Condition Programme 2026/2027 and approved the procurement of a capital condition programme for projects valued at an estimated £4.1m, funded by the DfE 2027/2028 School Condition grant. Authority was delegated to the Corporate Director - Inclusive Economy, Housing and Culture to increase the programme/spend if grant funding is higher than expected and to agree the scope of individual projects. Authority was also delegated to the Corporate Director of Children and Young People, in consultation with Cllr Lakmini Shah, to agree project substitutions within the overall budget.

Full council record

Decision

Decision:

For the reasons set out in this report and its appendices, Cabinet RESOLVED to:

i)  Accept £4,021,591 of grant funding from the Department for Education for the School Condition Programme 2026/2027.

ii)  The procurement of the proposed capital condition programme for projects set out in Appendix 1, funded from the DfE 2027/2028 School Condition grant at a total estimated value of £4.1m.

iii)  To delegate authority to the Corporate Director - Inclusive Economy, Housing and Culture to increase the programme /spend should the grant funding turn out to be a higher level than expected.

iv)  To delegate authority to the Corporate Director – Inclusive Economy, Housing and Culture to agree the scope of individual projects which have been identified by technical officers, to meet Health and Safety, compliance and replacement of antiquated systems to the school buildings.

v)  To delegate authority to the, the Corporate Director of Children and Young People in consultation with Cllr Lakmini Shah Cabinet Member for Children , Education and Communities to agree to substitute projects in response to changes in priorities, extensions or variations, to be limited to the total amount of the overall budget for the programme.

Alternatives Considered

i)  The projects identified in this report are those considered as being of a priority due to age and or potential failure that could impact on educational delivery at a school or have Health and Safety implications. Therefore, there is no real alternative other than replace the particular building element which has effectively reached the end of life.

ii)  The DfE funding is specifically provided for Local Authorities to undertake a regular programme of capital planned condition works each year to maintain and enhance the facility and contribute to the educational achievements obtained.

Related Meeting

Cabinet - Tuesday 17th November 2026 10.30 a.m. on November 17, 2026

Supporting Documents

- Schools_Capital_Condition_Programme Final .pdf
Copy of Proposed School Projects 2027 AOA.pdf

Details

ReferenceCall-ins0
OutcomeDecision approved
Decision date17 Nov 2026
Effective from25 Nov 2026
Subject to call-inYes