Approval to extend the completion date of the agreement under Section 278/38 of the 1980 Highways Act

December 13, 2023 Director: Communities (Other) Approved View on council website
Full council record

Decision

Authorisation given to extend the completion
date of the Agreement under Section 278/38 of the Highways Act 1980
for the residential development off Bridge Street, Brigg from 31
December 2023 to 31 December 2025 without amendment to the amount
of supporting bond.

Reasons for the decision

The completed S278/38 agreement supports
development and permits the council to adopt the roads, footways,
verges, swales, and highway drainage once the development has been
completed to the council’s requirements.

The S278/38 agreement can only legally last for two years and
requires an extension of time if works aren’t complete at the
end of the two year period. This development is not yet completed
and the agreement needs renewing.

Alternative options considered

N/A

Supporting Documents

Approval to extend completion date - Bridge Street Brigg.pdf

Details

OutcomeRecommendations Approved
Decision date13 Dec 2023