Decision
The bond amount securing the agreement under
Section 38 of the Highways Act 1980 to be reduced from
£404258.00 to £40425.00 with effect from 9th June 2025
on ER/Scunthorpe/28/08. Development off Dunlin Drive, Lakeside,
Scunthorpe.
Reasons for the decision
The S38 Agreement supports development and
permits the Council to adopt the roads, footways, verges, swales,
and highway drainage once the development has been completed to the
council's requirements.
Following a site inspection, the works are complete and the site
can be placed on a 12 month maintenance period, with the bond being
reduced to 10% of the original bond amount.