Decision
The bond amount securing the agreement under
Section 278/38 of the Highways Act 1980 to be reduced from
£94,540.00 to £9,454.00 with effect from 30 July 2025
on ER/Hibaldstow/23/01 Development off Ings Lane,
Hibaldstow.
Reasons for the decision
The S278/38 Agreement supports development and
permit the council to adopt the roads, footways, verges, swales,
and highway drainage once the development has been completed to the
council's requirements.
Following a site inspection, the works are complete and the site
can be placed on a 12 month maintenance period, with the bond being
reduced to 10% of the original bond amount.
Alternative options considered
Not applicable.