Procurement of Biomass Supplier

October 3, 2025 Director: Communities (Other) Key decision Approved View on council website
Full council record

Decision

To give approval to go out to procurement for
a biomass provider via use of the YPO framework.

Reasons for the decision

By using the YPO framework the council can
guarantee that the suppliers meet the wood pellet specifications
detailed in the DPS Terms and Conditions to work with the council
biomass generators.

Alternative options considered

To continue to use current suppliers on an as
need basis with the risk of no price security or contract
protection.

Details

OutcomeRecommendations Approved
Decision date3 Oct 2025