Approval to extend S38 Agreement - Spa Hill, Kirton Lindsey
October 28, 2025 Director: Communities (Other) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to extend the completion date of the Section 38 agreement for the residential development off Spa Hill, Kirton Lindsey, Phase 4, from October 31, 2025, to October 31, 2027, without changing the supporting bond amount.
Full council record
Decision
Authorisation given to extend the completion
date of the Agreement under Section 38 of the Highways Act 1980 for
the residential development off Spa Hill, Kirton Lindsey, Phase 4
from 31 October 2025 to 31 October 2027 without amendment to the
amount of supporting bond.
Reasons for the decision
The completed S38 agreement supports
development and permits the council to adopt roads, footways,
verges, swales, and highway drainage once the development has been
completed to the council's requirements.
The S38 agreement can only legally last for two years and requires
an extension of time if works aren't complete at the end of the two
year period. This development is not yet completed, and the
agreement needs renewing.
Alternative options considered
Not applicable
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 28 Oct 2025 |