Approval to extend S38 Agreement - South of Dunlin Drive, Scunthorpe

November 20, 2025 Director: Communities (Other) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to extend the completion date of the Section 38 agreement for the residential development south of Dunlin Drive, Scunthorpe, from November 30, 2025, to November 30, 2027, without changing the supporting bond amount.

Full council record

Decision

Authorisation given to extend the completion
date of the Agreement under Section 38 of the Highways Act 1980 for
the residential development off Lakeside, South of Dunlin Drive,
Scunthorpe from 30 November 2025 to 30 November 2027 without
amendment to the amount of supporting bond.

Reasons for the decision

The completed S38 agreement supports
development and permits the council to adopt the roads, footways,
verges, swales, and highway drainage once the development has been
completed to the council's requirements.

The S38 agreement can only legally last for two years and requires
an extension of time if works aren't complete at the end of the two
year period. This development is not yet completed and the
agreement needs renewing.

Alternative options considered

Not applicable.

Supporting Documents

Agreement to extend S38 Agreement - South of Dunlin Drive Scunthorpe.pdf

Details

OutcomeRecommendations Approved
Decision date20 Nov 2025