Approval to Extend the Completion Date of the Agreement Under Section 38 of the 1980 Highways Act - off Spa Hill, Kirton

February 11, 2026 Director: Communities (Other) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...the completion date of the Section 38 agreement for the residential development off Spa Hill, Kirton, phase 2 was extended from 28 February 2026 to 28 February 2028 without amendment to the supporting bond.

Full council record

Decision

Authorisation given to extend the completion
date of the Agreement under Section 38 of the Highways Act 1980 for
the residential development off Spa Hill, Kirton, phase 2 from 28
February 2026 to 28 February 2028 without amendment to the amount
of supporting bond.

Reasons for the decision

The completed S38 agreement support
development and permit the Council to adopt the roads, footways,
verges, swales, and highway drainage once the development has been
completed to the council’s requirements.
The S38 agreement can only legally last for two years and requires
an extension of time if works aren’t complete at the end of
the two year period. This development is not yet completed, and the
agreement needs renewing.

Alternative options considered

N/A.

Supporting Documents

OF Report - Approval to extend Completion Date - Off Spa Hill Kirton.pdf

Details

OutcomeRecommendations Approved
Decision date11 Feb 2026