Reduction to bond for development off Church Lane, Ulceby

November 7, 2023 Director: Communities (Other) Awaiting outcome View on council website
Full council record

Decision

The bond amount securing the agreement under Section 38 of the Highways Act 1980 to be reduced from £80,000.00 to £8,000.00 with effect from 30 October 2023 on ER/Ulceby/23/01 Development off Church Lane, Ulceby (rear of Co-op)

Reasons for the decision

The S38 Agreement supports development and permits the Council to adopt the roads, footways, verges, swales, and highway drainage once the development has been completed to the council’s requirements.

Following a site inspection, the works are complete and the site can be placed on a 12 month maintenance period, with the bond being reduced to 10% of the original bond amount.

Alternative options considered

N/A

Details

OutcomeFor Determination
Decision date7 Nov 2023