Extended completion date for the residential development at Redshank Drive and Turnstone Drive, Scunthorpe
November 7, 2023 Director: Communities (Other) Awaiting outcome View on council websiteFull council record
Decision
Authorisation given to extend the completion date of the Agreement under Section 38 of the Highways Act 1980 for the residential development at Redshank Drive and Turnstone Drive, off Lakeside Parkway, Scunthorpe from 31 October 2023 to 31 October 2025 without amendment to the amount of supporting bond.
Reasons for the decision
The completed S38 agreement support development and permit the Council to adopt the roads, footways, verges, swales, and highway drainage once the development has been completed to the council’s requirements.
The S38 agreement can only legally last for two years and requires an extension of time if works aren’t complete at the end of the two year period. This development is not yet completed and the agreement needs renewing.
Alternative options considered
N/A
Details
| Outcome | For Determination |
| Decision date | 7 Nov 2023 |