Extension of the completion date of the Agreement under Section 38 of the Highways Act 1980 for the residential development off Church Lane, Ulceby, from 30 May 2023 to 30 May 2025

June 13, 2023 Assistant Director Place (Deputy Director: Economy & Environment) (Officer) Awaiting outcome View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to extend the completion date of the Section 38 Highways Act agreement for the residential development off Church Lane, Ulceby, to May 30, 2025, without changing the supporting bond amount.

Full council record

Decision

Authorisation given to extend the completion
date of the Agreement under Section 38 of the Highways Act 1980 for
the residential development off Church Lane, Ulceby, from 30 May
2023 to 30 May 2025 without amendment to the amount of supporting
bond.

Reasons for the decision

The completed S38 agreement support
development and permit the Council to adopt the roads, footways,
verges, swales, and highway drainage once the development has been
completed to the council’s requirements. The S38 agreement
can only legally last for two years and requires an extension of
time if works aren’t complete at the end of the two year
period. This development is not yet completed and the agreement
needs renewing.

Alternative options considered

N/A

Supporting Documents

ODN Extend S38 Church Lane Ulceby.pdf
Decision Report Church Lane Ulceby.pdf

Details

OutcomeFor Determination
Decision date13 Jun 2023