Reduce the Bond Amount Securing the Agreement Under S278 of the Highways Act 1980

September 2, 2026 Director: Communities (Other) Approved View on council website
Full council record

Decision

The bond amount securing the agreement under Section 278 of the Highways Act 1980 to be reduced from £131,150.00 to £13,115.50 with effect from 28 July 2026 on ER/Brigg/35/01 Development off Wrawby Road, Brigg.

Reasons for the decision

The S278 Agreement supports development and permits the Council to adopt the roads, footways, verges, swales, and highway drainage once the development has been completed to the council’s requirements.
Following a site inspection, the works are complete, and the site can be placed on a 12 month maintenance period, with the bond being reduced to 10% of the original bond amount.

Alternative options considered

N/A.

Supporting Documents

Reduce the Bond Amount Securing the Agreement Under S278 of the Highways Act 1980 - Wrawby Road Bri.pdf

Details

OutcomeRecommendations Approved
Decision date2 Sep 2026