Reduce the Bond Amount Securing The Agreement Under S278 of the Highways Act 1980
October 23, 2026 Director: Communities (Other) Approved View on council websiteFull council record
Decision
The bond amount securing the agreement under Section 38 of the Highways Act 1980 to be reduced from £120,245.00 to £12,024.50 with effect from 24 August 2026 on ER/Barton/67/07 Development off Falkland Way, Barton, Phase 7.
Reasons for the decision
Following a site inspection, the works are complete, and the site can be placed on a 12 month maintenance period, with the bond being reduced to 10% of the original bond amount.
Alternative options considered
Not reducing the amount of the bond is not standard practice and could be subject to challenge by the developer.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 23 Oct 2026 |