Capital Budget Update
October 12, 2023 Executive (Other) Key decision Awaiting outcome View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
... to approve adjustments to the 2023/24 capital programme, including budget approvals for the Oakley Vale highway adoption and the North Northamptonshire Electric Vehicle Infrastructure project, as well as a reduction to the Integrated Transport Block scheme.
Full council record
Purpose
To report any adjustments to the in-year programme
Decision
RESOLVED
KEY DECISION
That the Executive:
i) Approved the following changes into the capital programme:
a. Oakley Vale, Corby Highway Adoption - £971k – budget approval for £971k, £495k in 2023/24, £476k in 2024/25 which is to be funded from external funds as part of the initial Infrastructure Agreement.
b. North Northamptonshire Electric Vehicle Infrastructure Project (NNEVI) £2.90m - £285k in 2024/25, £810k in 2025/26 and £1.8m in 2026/27 which is to be funded from an external grant.
c. Integrated Transport Block 2023/24 – reduction to existing capital scheme of £184k to align the scale of the programme with the confirmed grant funding from the Department of Transport.
Reasons for Recommendations: These are set out in greater detail within section 5 of the report but can be summarised as:
· To support the statutory delivery of school places and SEND school places across North Northamptonshire.
· To meet corporate plan objectives, for instance in leading in improving the local environment
Alternative Options Considered:
· As all the schemes in this report are grant funded/S106 funded, the use of the funding is in line with the agreements, so there are no alternative option proposed in this report.
· Where individual schemes are over £500k, individual reports are presented elsewhere on the agenda that set out the wider options that were considered before reaching the proposed schemes identified for grant funding.
Supporting Documents
Details
| Outcome | For Determination |
| Decision date | 12 Oct 2023 |
| Expected date | 12 Oct 2023 |
| Originally due | 12 Oct 2023 |