Family Hubs Programme Update

May 11, 2023 Approved View on council website
Full council record
Content

RESOLVED
 
That the Executive
noted:
 

a)     
Progress to date in meeting the key milestones, as
set out in Table 1 (section 4.7) which align with the DfE
requirements and grant terms.

 

b)     
The planed roll out of implementation of the
development of Family Hubs in NNC as set out in section 5.3 of the
report

 

c)     
The allocation and breakdown of the £4mgrant
funding secured for the Programme period 2022-25, and the process
to date of spend and carry over for 2022/23, as set out in Table 4
(section 7.1.3) of the report
 

 
Reason for
Recommendations – Consistency with previous decision resolved
by Executive on Thursday 15th September 2022 (see
section 8. Background Papers)

 

Alternative
Options Considered – The alternative option would be to not
provide an update and approve the allocation of the funding however
this option was discounted due to the nature of this report being
an Annual Update report and the need to allocate the funding as per
the Executive resolved decision on 15th September 2022
(see Section 8. Background Papers)

 

Supporting Documents

Family Hubs May 2023v5.pdf
Family Hubs - Appx A - Northants Data insight 0-19years.FINAL.pdf

Details

OutcomeRecommendations Approved
Decision date11 May 2023