Summary

...to approve changes to the capital programme, including budget approval for the Local Authority Housing Fund – Round 3, and noted other changes, drawdowns, and material items considered by the Strategic Capital Board.

Full council record

Purpose

To report any adjustments to the in-year programme.

Decision

RESOLVED

KEY DECISION

That the Executive:

a)        Approved the following changes into the capital programme:

i)    Local Authority Housing Fund – Round 3 (LAHF 3) - budget approval for £878k in 2025/26, £636k in the General Fund, £242k in the Housing Revenue Account (HRA) to be funded as follows:

£396k - Ministry of Housing, Communities and Local Government (MHCLG) grant

£240k – virement from existing LAHF round 1 capital scheme, previously approved discretionary funding

Overall increase to General Fund Capital Programme = £396k from new grant allocation  

£132k – MHCLG grant

£110k – virement from existing capital development/ acquisition budget, previously approved discretionary funding

Overall increase to HRA Capital Programme = None – change in funding mix within capital development/ acquisition budget 

b)        Noted the changes to the capital programme, following approval by Directorate Capital Boards / Departmental Management Team meetings, Chief Finance Officer (Section 151 Officer) and Strategic Capital Board (where applicable), as detailed in table 1 in the report.

c)         Noted the drawdowns of block budgets contained within the Capital Programme as detailed in table 2 in the report.

d)        Noted the other material items considered by Strategic Capital Board, as detailed in paragraphs 5.8 and 5.9 of the report.

Reasons for Recommendations – These are set out in the greater detail within section 5 of the report, but can be summarised as helping to meet the Council’s corporate plan objectives:

-       Green sustainable environment

-       Better, brighter futures

-       Safe and thriving places

-       Connected communities

-       Active, fulfilled lives

Alternative Options Considered – For those schemes which are grant funded or from Section 106 contributions, they are undertaken in accordance with the requirements of the grant conditions/ legal agreement and, therefore, there is no alternative option proposed in this report.

Related Meeting

Executive - Tuesday 12th August, 2025 10.00 am on August 12, 2025

Supporting Documents

Capital Programme Update 202526.pdf

Details

OutcomeFor Determination
Decision date12 Aug 2025
Expected date12 Aug 2025
Originally due12 Aug 2025