Mill Lane Primary School
October 7, 2026 Operational Manager – Cost Management & Major Projects (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Operational Manager – Cost Management & Major Projects approved recommendations on 07/10/2026. The decision appointed Beard under a JCT Pre Construction Services Agreement contract for £136,275.29.
Full council record
Purpose
This decision allows the Council to complete the RIBA stage 4 design and obtain firm construction costs to allow the demolition and replacement of aged and dilapidated temporary classrooms at Mill Lane Primary School with new purpose built accommodate to fulfil its statutory duty to provide Basic Need pupil places.
Decision
The decision has been made to appoint Beard under a JCT Pre Construction Services Agreement contract for the value of £136,275.29
Reasons for the decision
Beard provide the most economically advantageous tender in a competitive tender exercise on the Procure Partnership framework.
Alternative options considered
3 other tenderers submitted bids and were assessed in line with the framework rules and tender criteria.
Details
| Outcome | Recommendations Approved |
| Decision date | 7 Oct 2026 |