May 23, 2024 Delegated Decisions by Cabinet Member for Infrastructure & Development Strategy (Cabinet member) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to delegate authority to the Corporate Director of Environment & Place to appoint Galliford Try for design, planning, early contractor involvement, target cost setting, surveys, and investigation/enabling work support services for the Didcot Northern Perimeter Road (Section 3) scheme.
Full council record
Purpose
To
seek approval to appoint a contractor under an NEC4 Professional
Service Contract (PSC) Option A for planning, detailed design, ECI
and target cost setting and an NEC4 Engineering Construction Short
Contract (ECSC) for any enabling works, surveys and/or
investigation works (if required)
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 23 May 2024 |
| Subject to call-in | Yes |