Reinforced Autoclaved Aerated Concrete (RAAC) in Council Buildings
November 16, 2023 Finance, Policy and Resources Committee (Committee) Key decision Approved View on council websiteFull council record
Content
This Committee
resolved:
a)
To note the position regarding the presence of RAAC
across council buildings including schools and
also notes work being progressed to survey Council owned
non-school buildings.
b)
That the committee approves a positive revenue
budget addition of £25,000 in 2023/24 only, funded from the
central contingency budget, to cover the outstanding cost of phase
3 reviews.
c)
That the committee further notes that should the
completion of stage 3 reviews indicate the need for more detailed
assessments and potential remedial action at stages 4 or 5, then
there will be further requests for revenue or capital funding
brought forward as appropriate.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 16 Nov 2023 |