Bridgewater Street and Tully Street - Affordable Housing
March 10, 2025 Property / Regeneration Briefing (Other) Awaiting outcome View on council websiteFull council record
Decision
Salford City Council - Record of Decision
I Paul Dennett, City Mayor, in exercise of the powers contained within the City Council Constitution do hereby:
- Approve in principle, the disposal of 25 properties to Dérive RP Limited at Tully Street (10 units) and Bridgewater Street (15 units).
- Approve the provisional lending to Dérive RP Limited of £2.046m, to fund the acquisition of the completed scheme.
- Approve the proposed capital expenditure of £5.052m for the Council construction of the 25 units before the tender is let (subject to approval of Procurement Board).
- Note the previously approved award of £2.052m Single Homelessness Accommodation Programme grant funding, towards the delivery of this scheme.
- Note progress to date on the Homes England Affordable Housing Programme grant funding bid of £0.700m.
- Authorise the Shared Legal Service to prepare all necessary documentation and to take all steps which are required to give effect to the above recommendations.
The Reasons are: Following the successful application for Single Homelessness Accommodation Programme (SHAP) funding in November 2023 the City Mayor in May 2024 has previously approved the council entering into a grant agreement with Homes England to deliver 18 move on homes for young people at risk of homelessness. Provision was made within the capital programme to develop a detailed design for the scheme, obtain planning approval and appoint a contractor to provide firm scheme costs.
The report updates the Deputy City Mayor on the proposed scheme costs and that a separate Procurement Board report seeks approval to enter in to contracts to deliver the scheme.
Options considered and rejected were: none
Assessment of Risk:
· Failure to enter into a construction contract before 31st March 2025 will put the draw down of SHAP funding at risk
· Failure to secure AHP funding from Homes England
The source of funding is:
· Capital Programme 2024/25
· Homes England Single Homelessness Accommodation Programme grant funding
Legal Advice obtained: Kathryn Saldanha, Shared Legal Team
Financial Advice obtained: Grace Rogerson, Capital Finance Manager
Procurement Advice obtained: n/a the award of the contract to Seddon Construction to build the affordable homes was subject to a separate Procurement Board approval.
HR Advice obtained: n/a
Climate Change Advice obtained: Mike Hemingway - Principal Officer - Climate Change
The following documents have been used to assist the decision process:
Public/briefing report submitted to Property/Regeneration Briefing on 10th March 2025
Report to Cabinet on 13th July 2021 - Housing Delivery – Approval Of Matters Relating To Dérive RP’s Application to the Regulator for Social Housing and Business Plan
Contact Officer: Dylan Vince, Service Manager Assets and Developments
- This decision is not subject to consideration by another Lead Member.
- The appropriate scrutiny to call-in the decision is the Growth and Prosperity Scrutiny Panel
Signed: Paul Dennett
City Mayor
Dated: 10th March 2025
This decision was published on Monday 10th March 2025
This decision will come in force at 4.00 p.m. on Monday 17th March 202 unless it is called-in in accordance with the Decision Making Process Rules.
Related Meeting
Property / Regeneration Briefing - Monday, 10 March 2025 3.00 pm on March 10, 2025
Details
| Decision date | 10 Mar 2025 |
| Effective from | 18 Mar 2025 |
| Subject to call-in | Yes |