Approval to Award the Contract, PCSA for Affordable Housing Delivery Schemes (Joe Costello)
October 13, 2025 Key decision Awaiting outcome View on council websiteFull council record
Content
Salford City Council – Record of
Decision
(Procurement Board and Property and Regeneration
Panel)
Pre-Construction Services
Agreements and Costs for Affordable Housing Delivery
Schemes
I Councillor Jack Youd, Deputy City Mayor and Lead Member for Finance, Support Services and
Regeneration, in exercise of the powers contained within the City
Council Constitution, and
following consultation with appropriate elected members at the
Property/ Regeneration Briefing and Procurement Board,
do hereby:
Approve budget
of £647,589.00 for PCSA costs at site A2 Robert Hall Street,
Ordsall*
Approve the budget of £140,000 for PCSA costs at Edward
Avenue, Weaste and Seedley*
Approve the award the
contract for PCSA Costs for Affordable Housing Delivery Schemes, as
detailed in the table below^:
*
decision taken at Property/Regeneration Briefing held on
13th October 2025
Lead Service
Group
Place
How the contract was
procured?
(to be supplied by
procurement)
Direct Award/ Call
off
Framework Details (where
applicable)
(procurement body, framework
reference & title, start/ end date
Innovation Chain North Framework
(ICN)
Funding
Source
Capital Programme
Ethical Contractor (EC):
Mayor’s Employment Charter
Yes
EC: Committed to sign The
Mayor’s Employment Charter
Yes
EC: Committed to the principles
outlined in the Mayor’s Employment
charter
Yes
EC: Accredited Living Wage
Employer
Yes
EC: Committed to becoming
Accredited Living wage Employer
Yes
?
^
decision taken at Procurement Board meeting held on 13th
October 2025
Detail required
Answers
Title/Description of Contracted
Service/Supply/Project
Contract
for PCSA Costs for Affordable Housing Schemes
Procurement Reference numbers (DN and CR
number supplied by Procurement)
Name of Successful
Contractor
Seddon Construction
Supplier Registration Number
(to be supplied by Procurement
Proclass
Classification No.
(to be completed by
procurement)
Type of organisation
(to be supplied by
Procurement)
Choose an item.
Status of Organisation
(to be supplied by
Procurement)
Choose an item.
Contract Value (£)
£647,589
Total contract value £ (including
extensions)
£647,589
Contract Duration
12 months
Contract Start Date
20/10/2025
Contract End Date
20/10/2026
Optional Extension Period 1
TBA
Optional Extension Period 2
TBA
Who will approve each Extension
Period?
Executive Director (extension <
£150k)
Contact Officer (Name &
number)
Joe
Costello 0797641492
The Reasons:
are to advance
two affordable housing project.
Options considered and
rejected were:
none all procedures are in accordance with standing
orders.
Assessment of Risk: Medium
– should these project not proceed it will significantly
impact the next phases of affordable housing for the city, a key
priority.
Should the scheme not proceed,
for whatever reason, the costs within this report could become
abortive. The key risks to note surround programme and final cost
submission from the Council. Should these exceed current plans
further consideration to scheme viability and funding will be
needed.
Whilst there is confidence
future Homes England funding for affordable housing delivery will
be secured for the scheme, it should be noted this is not yet
secured and is a potential risk.
The source of funding
is: the Place Capital Programme.
Legal Advice
obtained: Tony Hatton, Solicitor, Shared
Legal Service –
25/09/2025.
Financial Advice
obtained: Grace Rogerson, Finance Manager
– 25/09/2025.
Procurement Advice
obtained: Antony Hilton, Strategic Head
of Procurement – 25/09/2025.
HR Advice
obtained: N/A.
Climate Change Advice
obtained: N/A.
Contact Officer:
Joe Costello - Senior Group
Lead(Housing Delivery Lead) Place, Property
Dylan Vince - Service Manager,
Assets and Development, Place, Housing Strategy
This matter is not subject to
consideration by another Lead Member.
The appropriate Scrutiny
Committee to call-in the decision is the Growth and Prosperity
Scrutiny Panel
Signed: Cllr J
Youd_
Deputy City Mayor and Lead Member for Finance, Support Services
and Regeneration
Dated:13th October 2025
·
This decision was
published on 14 October
2025.
·
This decision will
come in force at 4.00 p.m. on 21 October 2025 unless it is called-in in accordance with the
Decision Making Process Rules.
Related Meeting
Procurement Board - Monday, 13 October 2025 2.00 pm on October 13, 2025
Details
| Decision date | 13 Oct 2025 |
| Effective from | 22 Oct 2025 |
| Subject to call-in | Yes |