Approval to Award the Contract for Kearton Drive Retaining Wall Refurbishment (Mike Jolley)
October 27, 2025 Awaiting outcome View on council websiteFull council record
Decision
Salford City Council – Record of Decision
I Councillor Youd, Lead Member for Finance and Support Services and chairman of the Procurement Board, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby approve:
· to Award the Contract forKearton Drive Retaining Wall Refurbishment, as detailed in the table below:
Detail required
Answers
Title/Description of Contracted Service/Supply/Project
Kearton Drive Retaining Wall Refurbishment
Procurement Reference numbers (DN and CR number supplied by Procurement)
DN781932 / S1232-114
Name of Successful Contractor
The Casey Group Ltd.
Supplier Registration Number
(to be supplied by Corporate Procurement)
4233269
Proclass Classification No.
(to be completed by procurement)
391410
Type of organisation
(to be supplied by Corporate Procurement)
Private Limited Company
Status of Organisation
(to be supplied by Corporate Procurement)
SME
Contract Value
£241,622.54
Overall Scheme Value
£329,203.57 /full project
Contract Duration
11 weeks
Contract Start Date
05/01/2026
Contract End Date
20/03/2026
Optional Extension Period 1
N/A
Optional Extension Period 2
N/A
Who will approve each Extension Period?
Procurement Board (extension > £150k)
Contact Officer (Name & number)
Michael Jolley / 07718 248732
Lead Service Group
Place
How the contract was procured?
(to be supplied by procurement)
Technical & Highways Works Framework – Lot 4 – Structures & Bridges
Framework Details (where applicable)
(procurement body, framework reference & title, start/ end date
N/A
Funding Source
Capital Programme
Ethical Contractor (EC): Mayor’s Employment Charter
EC: Committed to sign up to charter
EC: Committed to sign The Mayor’s Employment Charter
EC: Accredited Living Wage Employer
EC: Committed to becoming Accredited Living wage Employer
The main works are Kearton Drive Retaining Wall Refurbishment.
Options considered and rejected were: Not to award the Contract.
Assessment of Risk: Low
Funding is sourced through Highways Capital Programme 2025/26 allocation for Structures 2025/26 budget.
The retaining wall is currently considered sub-standard, the proposed refurbishment works would ensure the safety of pedestrians, cyclists and vehicles whilst maintaining the life-cycle of the structure, which Salford City Council’s Engineering and Landscape Design Structures team are experienced in undertaking similar refurbishment schemes.
The source of funding is: Highways Capital Programme 2025/26.
Legal Advice obtained: 3 October 2025 – received from Tony Hatton, Principal Solicitor.
Financial Advice obtained: 13 October 2025 – received from Ian Cowburn, Senior Accountant.
Procurement Advice obtained: 7 October 2025 – received from Heather Stanton, Procurement Officer.
Contact Officer: Michael Jolley
Telephone number: 07718 248732
This matter is not subject to consideration by another Lead Member.
The appropriate Scrutiny Committee to call-in the decision is the Growth and Prosperity Panel.
Signed: Cllr J Youd Dated: 27 October 2025.
Lead Member
FOR DEMOCRATIC SERVICES USE ONLY:
* This decision was published on 27 October 2025
* This decision will come in force at 4.00 p.m. on 3 November 2025 unless it is called-in in accordance with the Decision Making Process Rules.
Related Meeting
Procurement Board - Monday, 27 October 2025 2.00 pm on October 27, 2025
Details
| Decision date | 27 Oct 2025 |
| Effective from | 4 Nov 2025 |
| Subject to call-in | Yes |