Proposed Extension to Technical and Highways Works Framework (Sharon Walls)
December 8, 2025 Key decision Awaiting outcome View on council websiteFull council record
Decision
Salford City Council – Record of Decision
I Paul Dennett, City Mayor, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby:
· to Award the Contract for Technical and Highways Works Framework, as detailed in the table below:
Detail required
Answers
Title/Description of Contracted Service/Supply/Project
Technical and Highways Works Framework 6month Extension
Procurement Reference numbers (DN and CR number supplied by Procurement)
Name of Successful Contractor
Name of Contractor
Type of Organisation
Registration No
Lot 1 - Minor Civils
- Argyle NW
Construction Ltd
- Colas Limited
- Rosgal Limited
- P Casey (Land Reclamation) Ltd
- Bethell Construction Limited
- Eric Wright Civil Engineering Ltd
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- 02829893
- 2644726
- 3731189
- 1122137
- 0264322
- 2565379
Lot 2 – Vehicle
Restraint System
- Coating Services
Ltd
- Protek Fencing Ltd
- Limited Company
- Limited Company
- 3852483
- 2197089
Lot 3 - Drainage
- Colas Limited
- Rosgal Limited
- General Utilities
Northwest Ltd
- AE Yates Ltd
- Bethell Construction Limited
- No Dig Drainage
Solutions Ltd
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- 2644726
- 3731189
- 6468779
- 415632
- 0264322
- 10378682
Lot 4 – Structures & Bridges
- P Casey (Land Reclamation) Ltd
- Eric Wright Civil Engineering Ltd
- Coating Services
Limited
-Amalgamated
Construction Ltd
(trading as
AmcoGiffen)
- AE Yates Ltd
- Bethell Construction
Ltd
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- 1122137
- 2565379
- 3852483
- 995892
- 415632
- 0264322
Lot 5 – Coring & Site Investigations
- Pavement Testing
Services Ltd
- Construction Testing Solutions Limited
- Concept Engineering Consultants Ltd
- Limited Company
- Limited Company
- Limited Company
- 04374737
- 05998333
- 03401367
Lot 6 – Landscaping
And Associated
- P Casey (Land Reclamation) Ltd
- Wright Landscapes
Ltd
- Horticon Ltd
- Groundwork
Landscape Ltd
- Landscape
Engineering Ltd
- Bethell Construction
Ltd
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- Limited Company
- 1122137
-04611247
- 2463376
- 1339901
- 04049863
- 0264322
Supplier Registration Number
(to be supplied by Procurement
Various
Proclass Classification No.
(to be completed by procurement)
390000
Type of organisation
(to be supplied by Procurement)
Other
Status of Organisation
(to be supplied by Procurement)
SME
Contract Value (£)
£ 10,000,000 per annum
Total contract value £ (including extensions)
£ 40,000,000
Contract Duration
12 months
Contract Start Date
06/02/2026
Contract End Date
05/08/2026
Optional Extension Period 1
6months (Lot 5 only)
Optional Extension Period 2
N/A
Who will approve each Extension Period?
Executive Director (extension < £150k)
Contact Officer (Name & number)
Sharon Walls
Lead Service Group
Place
How the contract was procured?
(to be supplied by procurement)
Other
Framework Details (where applicable)
(procurement body, framework reference & title, start/ end date
Open Tender on the Chest:
Technical and Highways Works Framework
Funding Source
Combination of Above (please detail below)
Ethical Contractor (EC): Mayor’s Employment Charter
Yes
EC: Committed to sign The Mayor’s Employment Charter
Yes
EC: Committed to the principles outlined in the Mayor’s Employment charter
Yes
EC: Accredited Living Wage Employer
Yes
EC: Committed to becoming Accredited Living wage Employer
Yes
The Reasons for the decision and report is to award a compliant contract that allows continuity of design and delivery of works to be commissioned and undertaken by suitably appointed contractors within the framework. An Exception to award and extension is being sought.
Options considered and rejected were – Salford is in the final year of a 4 year framework and requires additional time to ensure a compliant and fit fir purpose new framework is in place going forward. Alternative frameworks are available including the Bolton and Manchester Framework however, the availability of contractors who are already commissioned by other GM authorities cannot guarantee their commitment to deliver the scale of works required to be delivered during the extension period and the working relationships have not been established. Hence, this was the preferred procurement route. Work cannot be undertaken in-house as there are insufficient resources.
Assessment of Risk – by not having a contract in place Salford would not be able to deliver its financial commitments for 2025/26 and also 2026/27. The award of contract for a further 6months for the current framework is therefore essential in ensuring that Salford can continue to design and deliver a wide range of projects that will be funded from the capital and revenue programmes across the next 2 financial years.
The source of funding is a mixture of approved capital and revenue funding depending on the nature of work being undertaken.
Legal Advice obtained – The proposed award of the contract follows a call off exercise in accordance with the Council’s Technical and Highways Minor Civils Works Framework as referred to in the body of the report and legal supports the award.
Financial Advice obtained – Finance identifies the funding that is in place to deliver the likely projects to be undertaken. There remains sufficient headroom in the contract for projects to be commissioned by the council should it be needed.
Procurement Advice obtained - Yes.
HR Advice obtained – N/A.
Climate Change Implications obtained – N/A.
Contact Officer: Sharon Walls
Telephone number: 07598063732
The appropriate Scrutiny Committee to call-in the decision is the Growth and Prosperity Scrutiny Panel
Signed: Paul Dennett Dated: 8 December 2025.
City Mayor
FOR DEMOCRATIC SERVICES USE ONLY:
* This decision was published on 9 December 2025
* This decision will come in force at 4.00 p.m. on 16 December 2025 unless it is called-in in accordance with the Decision Making Process Rules.
Related Meeting
Procurement Board - Monday, 8 December 2025 2.00 pm on December 8, 2025
Details
| Decision date | 8 Dec 2025 |
| Effective from | 17 Dec 2025 |
| Subject to call-in | Yes |