Salford City Council – Record of
Decision
I Paul Dennett, City Mayor, in exercise of the powers contained within the
Council Constitution
do hereby approve:
·
the award of a 24-month Contract for Non-Half Hourly
(NHH) electricity supply to Drax Energy Solutions Limited,as
detailed in the table below:
Detail required
Answers
Title/Description of Contracted
Service/Supply/Project
NHH
contract for the supply of electricity
Name of Successful
Contractor
Drax Energy
Solutions Ltd
Supplier Registration Number
(to be supplied by Corporate
Procurement)
05893966
Type of organisation
(to be supplied by Corporate
Procurement)
Public Limited Company
Status of Organisation
(to be supplied by Corporate
Procurement)
Non-SME
Contract Value (£)
£1,070,824 Per annum (estimated
average)
Contract Duration
24 months
Contract Start Date
01/04/2024
Contract End Date
31/03/2026
Optional Extension Period 1
12 months
Optional Extension Period 2
months
Who will approve each Extension
Period?
Procurement Board (extension >
£150k)
Contact Officer (Name &
number)
Majid Maqbool
Lead Service Group
Place
How the contract was procured?
(to be supplied by
procurement)
Framework
Framework Details (where
applicable)
(procurement body, framework reference
& title, start/ end date
TC970 – Supply of electricity and electricity
related services
Funding Source
Revenue Budget
Ethical Contractor (EC): Mayor’s
Employment Charter
EC: Committed to sign Charter
EC: Accredited Living Wage
Employer
The Reasons are:
·
Following the procurement of NHH electricity supply
contract via a fully compliant Manchester Framework, prices were
obtained from the direct award supplier, Drax Energy Solutions for
12 and 24-month contract durations. The 24-month contract will
result in a cost of £1,070,824 per annum. This amounts to an
increase in annual costs of £457,473 (75%).
·
Options considered and rejected were a 12-month contract duration which would have
seen an increase of 63%, but with the cost differential only being
7% for the second year, this is considered as a relatively small
margin in present energy market conditions when factoring in the
potential risk to price increases together with
inflation.
·
The 24-month contract therefore provides budget
certainty for the next 2 years, thereby easing budget pressures and
offering protection from any short term price fluctuations arising
from any geopolitical events.
Assessment of Risk: Low.
The source of funding
is: General fund revenue budget
and school budgets.
Legal Advice obtained from: Tony Hatton, Principal
Solicitor.
Financial Advice
obtained from: Grace
Rogerson, Senior Accountant.
Procurement Advice obtained
from: Heather Stanton, Category Manager.
HR Advice obtained:
N/A.
Climate Change Implications
obtained from: Majid Maqbool, Energy Manager.
Contact Officer: Majid Maqbool
Telephone number: 0161 607 6987
The appropriate Scrutiny
Committee to call-in the decision is the Growth and Prosperity
Panel and overview Scrutiny Panel
Signed: Paul Dennett
Dated: 27 March
2024.
City
Mayor
FOR DEMOCRATIC SERVICES USE
ONLY
*
This decision was published on 8
April 2024
*
This decision will come in force at 4.00 p.m. on 15 April 2024
unless it is called-in in
accordance with the Decision Making Process Rules.
Details
| Outcome | Recommendations Approved |
| Decision date | 27 Mar 2024 |
| Subject to call-in | Yes |