Approval to enter into works enabling contract associated with Brownfield Land Release Grant and to extend the existing Pre-Construction Services Agreement for housing delivery at Robert Hall Street, Ordsall (Joe Costello)

March 27, 2024 Approved View on council website
Full council record
Content

Salford City Council – Record of
Decision
 
I Paul Dennett, City Mayor, in exercise of the powers contained within the
Council Constitution
do hereby approve:
 
·     
the award of the Contract forSite Enabling Works for
Housing Delivery at Robert Hall Street and West Park Street in
Ordsall, as detailed in the table below:
 

Detail required

Answers

Title/Description of Contracted
Service/Supply/Project

Site
Enabling Contract works at Robert Hall Street and West Park
Street

Name of Successful
Contractor

Countryside
Properties (UK) Limited

Supplier Registration Number

(to be supplied by Corporate
Procurement)

00614864

Type of organisation

(to be supplied by Corporate
Procurement)

Private Limited Company

Status of Organisation

(to be supplied by Corporate
Procurement)

Non-SME

Contract Value (£)

£3,095,584

Contract Duration

12-months

Contract Start Date

31/03/2024

Contract End Date

01/04/2025

Optional Extension Period 1

N/A

Optional Extension Period 2

N/A

Who will approve each Extension
Period?

Strategic Director (extension <
£150k)

Contact Officer (Name &
number)

Joe
Costello 07976 414 920

Lead Service Group

Place

How the contract
was procured?

(to be supplied by
procurement)

The Chest

Framework Details (where
applicable)

(procurement body, framework reference
& title, start/ end date

 

Funding Source

Combination of Above (please detail below)

Ethical Contractor (EC): Mayor’s
Employment Charter

 

EC: Committed to sign Charter

 

EC: Accredited Living Wage
Employer

 
A two-stage tender
process has been completed and was approved at Procurement Board on
10 January 2024 to approve the selection of a preferred contractor
and to award the PCSA for the project, Countryside Properties (UK)
Ltd (Vistry).
 
Brownfield Land
Release Funding from Department for Levelling Up, Housing and
Communities was secured for £3m to support site viability and
a Grant Funding Agreement was entered into by the Council on 1
August 2023.
 
The funding is for
infrastructure and remediation works and for the purposes of
delivering the project. In order to comply with grant funding
conditions, works contracts for funded activity must be signed by
31 March 2024 and evidenced by 12 April 2024.
 
Assessment of Risk: High, should the scheme not
proceed or is delayed it will significantly delay the next phases
of Affordable Housing for the City, a key priority. It will also
impact ongoing funding bids to support viability of schemes
including Brownfield Land Release Fund.
 
The source of funding
is:
Brownfield Land Release Funding from Department for Levelling Up,
Housing and Communities and Place Capital Programme; Housing
Delivery Development.
 
Legal Advice
obtained: The Shared Legal
Service 7 March 2024.
 
Financial Advice
obtained: The Finance Team
8 March 2024.
 
Procurement Advice obtained:
The Procurement Team 7 March 2024.
 
HR Advice obtained:
N/A.
 
Climate Change Implications
obtained: March 2024.
 
Contact Officer: Joe Costello
Telephone number: 07976 414 920
 
This matter is not subject to
consideration by another Lead Member.
 
The appropriate Scrutiny
Committee to call-in the decision is the Growth and
Prosperity.
 

Signed:    Paul Dennett
                 
Dated:    27 March
2024.
           
      City
Mayor
 

FOR DEMOCRATIC SERVICES USE
ONLY
 
*          
This decision was published on 2
April 2024.
*          
This decision will come in force at 4.00 p.m. on 9 April
2024 unless it is called-in in
accordance with the Decision Making
Process Rules.
 

Details

OutcomeRecommendations Approved
Decision date27 Mar 2024
Subject to call-inYes