SBNI DP7 A580 Junctions

September 27, 2023 Approved View on council website
Full council record
Content

Salford City Council – Record of
Decision
 
I Paul Dennett, City
Mayor, in exercise of the powers
contained within the Council Constitution do hereby approve:
 
·     
The award of tender for SBNI Delivery Package 7
(DP7) to AE Yates for the reason(s), highlighted in the table
below:
 

Detail required

Answers

Title/Description of Contracted
Service/Supply/Project

Salford Bolton Network Improvements (SBNI) –
Package 7 (DP7) A580 Junctions

Name of Successful
Contractor

AE Yates

Supplier Registration Number

(to be supplied by Corporate
Procurement)

00415632

Type of organisation

(to be supplied by Corporate
Procurement)

Private Limited Company

Status of Organisation

(to be supplied by Corporate
Procurement)

SME

Contract Value (£)

£1,285,632

Contract Duration

6 months

Contract Start Date

08/01/2024

Contract End Date

28/06/2024

Optional Extension Period 1

months

Optional Extension Period 2

months

Who will approve each Extension
Period?

Choose an item.

Contact Officer (Name &
number)

Lead Service Group

Place

How the contract
was procured?

(to be supplied by
procurement)

Mini Competition

Framework Details (where
applicable)

(procurement body, framework reference
& title, start/ end date

STAR Framework

Funding Source

Grant

Ethical Contractor (EC): Mayor’s
Employment Charter

 

EC: Committed to sign Charter

 

EC: Accredited Living Wage
Employer

 
The Reasons are:
The proposed work on SBNI DP7 form
one of the Delivery Packages for the SBNI programme.
The objectives of the programme are to improve the punctuality,
regularity and reliability of bus services in the region and
promote active, healthy lifestyles and make sustainable travel
safer and easier to use and an attractive alternative to the
private car. This is aligned with Greater Manchester Transport
Strategy objectives and will provide positive impacts on the
recently launched Bee Network bus services that will use these
routes in Salford.
 
Options considered and rejected
were:
not to award the contract
 
Assessment of Risk: Medium
 
The source of funding
is: Greater Manchester Combined
Authority
 
Legal Advice obtained: Tony Hatton
 
Financial Advice
obtained: Hollie
Faulkner
 
Procurement Advice obtained:
Heather Stanton
 
HR Advice obtained:
N/A
 
Climate Change Implications
obtained: Mike Hemingway / Opu Anwar
 
The following documents have
been used to assist the decision process:
·     
Report to the City Mayor’s Regeneration
Briefing – 13July 2015
·     
Urban Vision – Regeneration Panel Presentation
– July 2016
·     
Report to Lead Member for Planning & Sustainable
Development – 14th April 2020
·     
Report to Procurement Board 19th February
2020
·     
Report to Procurement Board 11th January
2023
 
Contact Officer: Opu Anwar
Contact: opu.anwar@salford.gov.uk
 
Please delete from the bullets
below any which are not relevant:
·     
This matter is not subject to consideration by
another Lead Member.
·     
The appropriate Scrutiny Committee to call-in the
decision is the Growth and Prosperity Scrutiny
Committee.
 

Signed:   Paul
Dennett      Dated:     27 September 2023.
           
     City
Mayor
 

FOR DEMOCRATIC SERVICES USE
ONLY
 
*          
This decision was published on 29 September 2023
*          
This decision will come in force at 4.00 p.m. on 7 October 2023
unless it is called-in in accordance with the Decision Making Process Rules.
 

Details

OutcomeRecommendations Approved
Decision date27 Sep 2023
Subject to call-inYes