Approval to award the contract for the supply of natural gas to all council premises

June 14, 2023 Approved View on council website
Full council record
Content

Salford City Council – Record of
Decision
 
I Paul Dennett, City Mayor, in exercise of the powers contained within the
Council Constitution do hereby
approve:
 
·     
to award the contract for
the supply of natural gas to all council premises, as detailed
below:
 

Detail required

Answers

Title/Description of Contracted
Service/Supply/Project

Contract
for the supply of natural gas

Name of Successful
Contractor

Corona
Energy

Supplier Registration Number

(to be supplied by Corporate
Procurement)

0324101

Type of organisation

(to be supplied by Corporate
Procurement)

Public Limited Company

Status of Organisation

(to be supplied by Corporate
Procurement)

Non-SME

Contract Value (£)

£5,583,776      full project

Contract Duration

24 months

Contract Start Date

01/07/2023

Contract End Date

30/06/2025

Optional Extension Period 1

12 months

Optional Extension Period 2

months

Who will approve each Extension
Period?

Procurement Board (extension >
£150k)

Contact Officer (Name &
number)

Majid
Maqbool

Lead Service Group

Place

How the contract was procured?

(to be supplied by
procurement)

Framework

Framework Details (where
applicable)

(procurement body, framework reference
& title, start/ end date

YPO Gas framework ref 986

Funding Source

Revenue Budget

Ethical Contractor (EC): Mayor’s
Employment Charter

 

EC: Committed to sign Charter

 

EC: Accredited Living Wage
Employer

 
The Reasons are following the procurement of gas
renewal via a fully compliant YPO framework, Corona Energy
submitted prices for both 12 and 24 months. The 24-month contract
provides best value and will result in a total cost of
£5,583,776. This amounts to a reduction in costs of
£4,174,978 (47%) for the term of the contract.
 
Options considered and rejected
was a 12-month contract which
would have limited the cost reductions to 44%.
 
The 24-month contract therefore
provides budget certainty and an overall cost reduction that will
help in easing budget pressures over the course of next 2
years.
 
Assessment of Risk: Low
 
The source of funding
is: Revenue budgets and
schools’ budgets
 
Legal Advice obtained from: Tony Hatton, Principal
Solicitor
 
Financial Advice
obtained from: Gemma
Singleton, Senior Accountant
 
Procurement Advice obtained
from: Heather Stanton, Category Manager
 
HR Advice obtained:
N/A
 
Climate Change Implications
obtained from: Majid Maqbool, Energy Manager
 
Contact Officer: Majid Maqbool
Telephone number: 0161 607 6987
 
The appropriate Scrutiny
Committee to call-in the decision is the Growth and Prosperity
Panel and overview Scrutiny Panel
 
 

Signed:     Paul
Dennett    Dated:     14 June
2023.
           
       
City Mayor
 

FOR DEMOCRATIC SERVICES USE
ONLY
 
*          
This decision was published on 14 June 2023
*          
This decision will come in force at 4.00 p.m. on 21 June 2023
unless it is called-in in
accordance with the Decision-Making Process Rules.
 

Details

OutcomeRecommendations Approved
Decision date14 Jun 2023
Subject to call-inYes