Housing Development at Robert Hall Street, Ordsall - Appointment of Contractors
September 14, 2026 Awaiting outcome View on council websiteFull council record
Decision
Salford City Council - Record of Decision
Affordable Housing Development - A2 Robert Hall Street, Ordsall
I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning, Transport, Sustainable Development and Regeneration, in exercise of the powers contained within the City Council Constitution, and following consultation with Cabinet, do hereby approve:
- Approve the funding mix for the scheme as detailed in the report including the
proposed capital expenditure within the Housing Strategy Capital Programme.
- Approve entering into a Grant Funding agreement with the Greater Manchester
Combined Authority (GMCA) for Good Growth Funding support.
- Approve The Council obtaining grant funding from Homes England under its
Social and Affordable Homes Programme (SAHP) on the basis detailed in the
accompanying report.
- Delegate authority to the Executive Director of Place in consultation with the
S151 officer to: negotiate, agree, and finalise the detailed terms of the
transaction and funding agreements, including any required variations to the
currently proposed funding mix.
- Authorise the Shared Legal Service, or externally appointed solicitors, to
prepare all necessary documentation and to take all steps which are required to
give effect to the above recommendations.
- That the decision of the Procurement Board of 14th September 2026 approving
the appointment of Seddon Construction (which is subject to and conditional on
confirmation of grant funding from Homes England and the GMCA), be noted.
The Reasons are approval will enable the Council to finalise funding arrangements, progress the construction contract and commence delivery of the scheme in accordance with the programme, supporting the Council's commitment to increasing the supply of affordable homes and creating sustainable communities across Salford.
All procedures are in accordance with standing orders.
Options considered and rejected were: None.
Assessment of Risk:
Medium - should this project not proceed it will significantly impact the next phases of affordable housing for the city, a key priority.
The source of funding is: Housing Capital Programme 2026/27
Legal Advice obtained:
Jason Scott Shared Legal Service - 12/08/2026
Financial Advice obtained:
Adam Mozley - 12/08/2026
Procurement Advice obtained:
N/A
HR Advice obtained:
N/A
Climate Change Advice obtained:
N/A
Contact Officer:
Joe Costello
Senior Group Lead, Housing Delivery, Regen Group, Place Directorate
Email: joe.costello@salford.gov.uk
- This decision is not subject to consideration by another Lead Member.
- The appropriate scrutiny to call-in the decision is the Growth and Prosperity Scrutiny Panel
Signed: Councillor Mike McCusker
Deputy City Mayor and Lead Member for Planning, Transport, Sustainable Development and Regeneration
Dated: 14th September 2026
This decision was published on Monday 14th September 2026
This decision will come in force at 4.00 p.m. on Monday 21st September 2026
unless it is called-in in accordance with the Decision Making Process Rules.
Related Meeting
Property / Regeneration Briefing - Monday, 14 September 2026 - 3.00 pm on September 14, 2026
Details
| Decision date | 14 Sep 2026 |
| Effective from | 22 Sep 2026 |
| Subject to call-in | Yes |