Approval to Increase the Delegated Approval Threshold for Contracts Awarded Via the Technical and Highway Works Framework (Steve Hands/ Sharon Walls)

November 23, 2026 Awaiting outcome View on council website
Full council record

Decision

Salford City Council – Record of Decision

I Paul Dennett, City Mayor, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby:

·     approve the Delegation of Authority for Contract Awards under the Technical and Highway Works Framework, as detailed in the table below:

Detail required

Answers

Title/Description of Contracted Service/Supply/Project

Delegation of Authority for Contract Awards under the Technical and Highway Works Framework

Procurement Reference Number (DN and CR, supplied by Procurement)

DN780443 / S2132

Name of Successful Contractor

Name of Contractor

Type of Organisation

Registration No

Lot 1a– Minor Civils

TBC

TBC

Lot 1b – Major Civils

TBC

TBC

Lot 2 – Specialist Surfacing

TBC

TBC

Lot 3 – Bridges &Structures

TBC

TBC

Lot 4 – Landscaping

And Associated

Services

TBC

TBC

Supplier Registration Number

(to be supplied by Lead officer)

Various

Supplier Identifier Reference (Central Digital Platform) above awards above £30,000 (inc VAT)

Various

Proclass Classification No.

(to be completed by procurement)

390000

Type of organisation

(to be supplied by Lead Officer)

Other

Status of Organisation

(to be supplied by Lead Officer)

Choose an item.

Contract Value (£)

£          10,000,000 per annum (estimated)

Total Contract Value including extensions (£)

£          200,000,000 (maximum framework value)

Contract Duration

8 years

Contract Start Date

01/04/2027

Contract End Date

31/03/2035

Optional Extension Period 1

Months

Optional Extension Period 2

Months

Who will approve each Extension Period?

Procurement Board (extension > £150k)

Contact Officer (Name & number)

Sharon Walls / Stephen Hands

Lead Service Group

Place

Procurement Legislation

PA2023

Funding Source

Combination of Above (please detail below)

Ethical Contractor (EC): Mayor’s Employment Charter

Yes

EC: Committed to sign up to the Mayor’s Employment Charter

Yes

EC: Committed to the principles outlined in the Mayor’s Employment charter

Yes

EC: Accredited Living Wage Employer

Yes

EC: Committed to becoming Accredited Living Wage Employer

Yes

The Reasons are:

To allow the Deputy Chief Executive (Executive Director of Place) to approve the direct awards of contracts up to the increased threshold for Minor Civils works under the new framework.

Options considered and rejected were: N/A.

Assessment of Risk:

If the increase in the level of delegated authority to match the threshold for the direct award of works via the new Technical and Highway Works Framework is not approved Salford will be at risk of not being able to deliver planned and agreed future programmes of work. There will therefore be slippage in budget spend during any given financial year due to the added competition requirements associated with retaining a lower fixed threshold.

This risk will likely then extend into future financial years and programmes yet to be agreed with programmes and schemes not being able to be fully delivered having a likely knock on effect into future years.

There is a risk that we would not be able to deliver schemes and works that are grant funded with specific deadlines for delivery e.g. GMCA / TfGM. Salford could in effect lose future funding and the lack of spend could risk securing expected or funding from future settlements.

Some works are also required to be undertaken to ensure that the council meets its statutory duties with regard to maintaining highway assets and hence could be subject to increased insurance liability due to delays in delivery.

The added burden on staff to undertake the increasing amount of competitions and gain approvals will mean that more staff would need to be employed to undertake the tasks adding further cost pressures to the programme meaning less work undertaken on the ground. Due to recruitment pressures currently experienced this is likely to result in added pressure on existing resource and hence likely slippage in overall delivery.

Innovate/ Best Value – identify the relevant corporate priorities specific to Salford:

·     Capital Programme Delivery

·     Corporate Plan 2024-2028

·     Greater Manchester Transport Strategy 2050

The source of funding and financial advice obtained:

The funding associated with the works delivered through the new Technical and Highways Framework is expected to be primarily from Unsupported Borrowing, Devolved Budget allocations and Capital Grants of the order of £10m p.a. Smaller works are funded via revenue.

There are no specific financial implications arising from this request.

Legal Advice obtained:

The City Mayor may amend and extend the delegations to an officer and this will require to be recorded in the Mayor’s Register of Executive Decisions delegated to Chief Officers

Procurement Advice obtained:

As above this report outlines the detail around the direct award of schemes within the new Technical and Highways Works Framework up to the value of £150k with the addition of the BCIS index to be amended on an annual basis in line with the anniversary of the framework award.  As explained this is to ensure the smooth running of the depot who have an increasing amount of work which lies just outside the governance of £150k due to market forces in recent years. 

HR Advice obtained: N/A.

Climate Change Implications obtained: N/A.

Documents

The following documents have been used to assist the decision process:

·     Report and Record of Decision: Contract Award – Technical Services and Highway Works Framework 14th December 2021 

·     Report and Record of Decision: Approval to go out to competition for the Technical & Highways Framework 2026-2034 8 September 2025

·     Report and Record of Decision: Proposed Extension to Technical and Highways Works Framework 8 December 2025

·     Report and Record of Decision: Proposed Extension to Technical and Highways Works Framework 6 August 2026

Contact Details:

·     Contact Officer: Sharon Walls / Stephen Hands

·     Telephone number: 07598063732 / 07809085252

Please delete from the bullets below any which are not relevant:

·     This matter is not subject to consideration by another Lead Member.

Signed:    Paul Dennett      Dated:    23 November 2026.

               City Mayor

FOR DEMOCRATIC SERVICES USE ONLY:

·     This decision was published on 23 November 2026.

·     This decision will come in force at 4.00 p.m. on 30 November 2026 unless it is called-in in accordance with the Decision Making Procedure Rules.