Approval to award contract for the delivery of the Oldfield Road Corridor Improvement scheme (Anene Chiegboka/ Lee Evans)
November 23, 2026 Key decision Awaiting outcome View on council websiteFull council record
Decision
Salford City Council – Record of Decision
I Paul Dennett, City Mayor, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby:
· approve and award the Contract for the Oldfield Road Corridor scheme, as detailed in the table below
· approve the appointment of Bethell Group plc, subject to approval of the Shift Statement associated with the August 2024 approved full business case by TfGM’s Active Travel Programme Board and funding approval by the Bee Network Committee.
· approve the creation of a purchase order to Bethell Group plc for £3,116,216.76 to facilitate payments under the construction contract.
· approve the creation of purchase orders for Other Project Costs totalling £540,034.15, comprising:
o £170,034.15 payable to Greater Manchester Combined Authority (c/o Transport for Greater Manchester) for the supply and installation of traffic signal equipment.
o £370,000.00 for construction phase project management and supervision services.
· approve the utilisation of the project risk allowance budget, as indicated in the report, to meet associated project delivery costs, where required.
, as detailed in the table below:
Answers
Title/Description of Contracted Service/Supply/Project
Oldfield Road Corridor
Procurement Reference numbers (DN and CR number supplied by Procurement)
DN823671/S2008
Name of Successful Contractor
Bethell Group PLC
Supplier Registration Number
2281508
Supplier Identifier Reference
(Central Digital Platform FTS) for awards above £30,000 (inc VAT)
PCWV-7645-GQPY
Proclass Classification No.
(to be completed by procurement)
391411
Type of organisation
Private Limited Company
Status of Organisation
SME
Contract Value (£)
£3,116,216.76
Total contract value £ (including extensions)
£3,116,216.76 total project value
Contract Duration
9 months
Contract Start Date
01/02/2027
Contract End Date
22/10/2027
Optional Extension Period 1
Not Applicable
Optional Extension Period 2
Not Applicable
Who will approve each Extension Period?
Executive Director (extension < £150k)
Contact Officer (Name & number)
Regina Otero Pose
Lead Service Group
Place
How the contract was procured?
(to be supplied by procurement)
ITT
Procurement Legislation
Choose an item.
Framework Details (where applicable)
(procurement body, framework reference & title, start/ end date
LOT 1 – General Civil Engineering Works of Bolton Highways Framework Contract 2024 – 2028
Funding Source
Active Travel Fund and Section 106 Local Contribution
Ethical Contractor (EC): Mayor’s Employment Charter
No
EC: Committed to sign The Mayor’s Employment Charter
Yes
EC: Committed to the principles outlined in the Mayor’s Employment charter
Yes
EC: Accredited Living Wage Employer
No
EC: Committed to becoming Accredited Living wage Employer
Yes
The Reasons are:
The Oldfield Road Corridor Scheme will deliver a high-quality active travel corridor between Chapel Street and Regent Road, improving walking, wheeling and cycling and connectivity to key residential, employment and regeneration areas.
Approval is required to award the delivery contract, enabling progress on this key corridor route to create an attractive, safe and accessible corridor that encourages walking and cycling as everyday travel choices.
Options considered and rejected were: None.
Assessment of Risk: Low - the contractors on the Bolton Highways Framework Contract have a successful track record of delivering schemes on behalf of the City Council.
The source of funding and financial advice obtained: The scheme will be funded from a combination of funding sources, which includes:
· £1,153,898.86 of allocated Section 106 Local Contribution.
· £2,409,348.95 Salford City Council’s Virement to the Active Travel Fund programme.
· £4,320,000 of Active Travel Fund Tranche 3.
Financial Advice obtained: Yes – received from Ian Cowburn, Senior Accountant.
Legal Advice obtained: Yes – received from Daniel Howard, Principal Lawyer.
Procurement Advice obtained: Yes – received from Heather Stanton, Category Manager.
HR Advice obtained: N/A.
Climate Change Implications obtained: Yes, received from Michael Hemingway, Principal Officer Climate Change.
Contact Officer: Anene Chiegboka.
Signed: Paul Dennett Dated: 23 November 2026.
City Mayor
FOR DEMOCRATIC SERVICES USE ONLY:
· This decision was published on 23 November 2026.
· This decision will come in force at 4.00 p.m. on 30 November 2026 unless it is called-in in accordance with the Decision Making Procedure Rules.
Related Meeting
Procurement Board - Monday, 23 November 2026 2.00 pm on November 23, 2026
Details
| Reference | 0 |
| Decision date | 23 Nov 2026 |
| Effective from | 1 Dec 2026 |
| Subject to call-in | Yes |