Phase 1 Demolition Area – Eccles Shopping Centre (Sarah Malone)
November 25, 2024 Approved View on council websiteFull council record
Content
Salford City Council – Record of
Decision
I, Paul Dennett, City Mayor, in exercise of
the powers contained within the Council Constitution do hereby approve:
·
a cost variation in the current Phase 1 Eccles
Shopping Centre Demolition to enable the properties (shown coloured
on the plan attached to the report) to be retained until a later
date, as detailed in the table below:
Detail
required
Answers
Title/Description of Contracted
Service/Supply/Project
Phase 1 Eccles Shopping Centre,
Eccles, shown edged blue on the attached plan.
Name of Successful
Contractor
Connell
Brothers Limited
Supplier Registration
Number
(to be supplied by Corporate
Procurement)
247
5702
Type of
organisation
(to be supplied by Corporate
Procurement)
Private Limited
Company
Status of
Organisation
(to be supplied by Corporate
Procurement)
SME
Tendered Contract
Value
£578,280
Full Project
£641,280,
Client Contingency for Removal of
Unidentified Asbestos
£500,000
Full Project commitment
£1,141,280
Proposed new contract
price
£821,280.00, including increased costs to enable
the retention of the remaining occupied properties, prelims and
fencing, partial asbestos removal based on limited surveys and
contractor’s contingency.
Client
Contingency
Removal of unidentified asbestos
£500,000
An allowance for potential additional
works to the retained properties which may result from partial
demolition works
£120,000
Full Project
commitment
£1,441,280 (increase of
£300,000)
Vat
Vat will be charged at the standard
rate of 20% unless stated otherwise.
Contract
Duration
The contract was originally 32 weeks
with an allowance of twelve months to allow for delays. This allowance should remain the same as the
contractor has made an allowance of an additional 6 weeks to the
programme to reflect the retention of the units to be
retained.
Contract Start
Date
06/01/2025
Contract End
Date
05/01/2026
Contact Officer (Name &
number)
Sarah Malone t. 07977 674683
Lead Service
Group
Place
Funding
Source
Capital Programme
The Reasons are:
Vacant possession has been achieved for the
majority of properties across the Phase 1 area but despite ongoing
negotiations with the remaining tenants it has not been possible to
achieve possession of all properties to date. The proposed cost
variation will reflect the complexities in the demolition works and
revised programme to work around those properties, if
required.
Options considered and rejected were: None. All procedures are in accordance
with normal Contractual Standing Orders.
Assessment of
Risk: Medium to
high.
There are risks attached with partial demolition
but a contingency has been allocated and officers continue to
mitigate any risks as more information become
available.
The source of funding is: 2024/2025 Capital
Programme (Expenditure Code: Eccles Capital Code
A70419).
Legal Advice obtained. Supplied by: The Shared Legal Service –
Contact officer and telephone number: Tony Hatton 219
6323.
Financial Advice
obtained. Submitted
by: The Finance Team – Contact
officer and telephone number: Daniel
Hillman, 793 2284.
Procurement
Advice obtained: Supplied by: The
Corporate Procurement Team Contact officer and telephone number:
Daniel Cunliffe (Category Manager – Corporate Procurement
Team) Tel: 0161 686 6249.
HR Advice
obtained: N/A.
Climate Change
Implications: Mike Hemmingway.
The following
documents have been used to assist the decision
process:
·
Report to Procurement Board dated 25th
November 24.
Contact Officer: Sarah Malone.
Telephone
number: 07977 674
683.
·
This matter is not subject to consideration by
another Lead Member.
·
The relevant Scrutiny Committee to call-in this
decision is the Growth and Prosperity Scrutiny
Panel.
Signed: Paul Dennett
Dated: 25 November
2024.
City
Mayor
FOR DEMOCRATIC
SERVICES USE ONLY
*
This decision was published on 27 November 2024.
*
This decision will come in force at 4.00 p.m. on 4 December
2024 unless it is called-in in
accordance with the Decision Making Process
Rules.
Related Meeting
Procurement Board - Monday, 25 November 2024 2.00 pm on November 25, 2024
Details
| Outcome | Recommendations Approved |
| Decision date | 25 Nov 2024 |
| Subject to call-in | Yes |