Allocation of Climate Change Reserve funding

February 16, 2024 Deputy Chief Executive, Section 151 Officer (Officer) Approved View on council website
Full council record

Purpose

To seek approval for funding from the Climate
Change Reserve to be used for the installation of new pool covers
at Leisure Centres in Grantham, Bourne and Stamford.

Decision

That a contract is awarded to Forge Leisure for
the design and installation of new pool covers at Bourne,
Stamford and Grantham Leisure Centres.
 

The funding of the pool covers will be a combination of external
funding secured (in respect of the Grantham Meres Leisure Centre
pool cover) and use of the established Climate Change
Reserve.  The value of work to install
new pool covers at the three centres is £116,357 which is a
combination of reserve £69,632 and external funding of
£46,725.00.
 

Supporting Documents

ODD pool covers V3.pdf

Details

OutcomeRecommendations Approved
Decision date16 Feb 2024