Wellington Way, Market Deeping - Approval of Contract Sum Increase
February 10, 2026 Cabinet (Cabinet collective) Key decision Approved View on council websiteFull council record
Purpose
To increase the approved construction contract sum for the Wellington Way new build housing scheme by £190,000, following the findings of a recent site investigation and technical report undertaken after contract award.
To seek delegated authority to the Council’s Section 151 Officer, in consultation with the Leader of the Council, to approve up to a further 10% additional funding should unforeseen costs arise during delivery of the project.
Related Meeting
Cabinet - Tuesday, 10th February, 2026 4.00 pm on February 10, 2026
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 10 Feb 2026 |
| Effective from | 19 Feb 2026 |
| Expected date | 10 Feb 2026 |
| Originally due | 10 Feb 2020 |
| Lead officer | Suniel Pillai |
| Subject to call-in | Yes |