Use of Housing Revenue Account (HRA) Capital Receipts Reserve

September 3, 2026 Deputy Chief Executive, Section 151 Officer (Officer) Approved View on council website
Full council record

Purpose

To seek approval for the allocation of £140k from the HRA Capital Receipts Reserve to fund the installation of Mechanical Ventilation with Heat Recovery (MVHR) systems (£73k) and the increased cost for the connection of utilities (£67k) at the Larch Close Grantham development.

Decision

To approve the allocation of £140k from the HRA Capital receipts reserve to fund the installation of Mechanical Ventilation with Heat Recovery (MVHR) systems (£73k) the increased cost for the connection of utilities (£67k) at the Larch Close Grantham development.

Supporting Documents

Use of HRA Capital Receipts Reserve ODD - final.pdf

Details

OutcomeRecommendations Approved
Decision date3 Sep 2026