Cabinet Members' Items - Report of the Economic Growth, Regeneration & Tourism Portfolio Holder - A.7 - Community Regeneration Partnership - Programme Update and further wave of Projects

March 17, 2025 Cabinet (Cabinet collective) Awaiting outcome View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Cabinet decided on 17/03/2025 to approve the scope and details of second and third wave projects for implementation. Cabinet authorised specific Portfolio Holders to approve procurement strategies and contract awards for various projects including Public Open Spaces in Jaywick and the Martello Tower E project. Cabinet also approved the establishment of the Regeneration Capital Delivery Board as the programme governance board.

Full council record

Decision

RESOLVED that Cabinet -

(a)   approves the scope and details of the ‘second’ and ‘third’ wave projects set out in Table 2 of this report (A.7) for implementation and that the following delegations are based upon the information as set out in Table 2;

(b)   authorises the Portfolio Holder for Economic Growth, Regeneration and Tourism in consultation with:

(i)    the Portfolio Holder for Portfolio Holder for Leisure & Public Realm, to approve the detailed brief and procurement strategy through to contract award for delivery for the Public Open Spaces in Jaywick project (Ten_09);

(ii)   the Portfolio Holder for Assets & Community Safety, to agree the procurement strategy through to contract award for delivery of the Martello Tower E project (Ten_11);

(iii)  the Portfolio Holder for Leisure & Public Realm, to proceed to agree the procurement strategy through to award of contract for the Active Wellbeing Centre Phase 1 project, incorporating urgent repairs (Ten_12);

(iv)  the Portfolio Holder for Arts, Culture & Heritage, to approve the detailed brief and procurement strategy through to award of contract for delivery of the Spatial Plan for Culture project (Ten_14);

(v)   the Portfolio Holder for Leisure & Public Realm, to approve the detailed brief and procurement strategy through to award of main building contract(s) for the Active Wellbeing Centre Phase 1 project subject to the outcome of a formal procurement process;

(vi)  for the Sunspot Solar Panels project (Ten_04) authority is delegated to the Portfolio Holder for Economic Growth, Regeneration and Tourism to agree the procurement strategy through to award of contract for completion of the project;

(c)   requests the procurement strategy for each of the projects to specify the relevant Social Value Themes, Outcomes and Measures in accordance with the Council’s adopted policy;

(d)   accepts the £60,000 grant received from the Ministry for Housing, Communities and Local Government LUF Capacity and Capability fund and allocates the sum in full to the budget established for the Project Delivery Unit;

(e)   approves that the Regeneration Capital Delivery Board (RCDB) be formally established as the programme governance board with authority for the Community Regeneration Partnership and authorises the Portfolio Holder for Regeneration, Economic Growth and Tourism to approve the final terms of reference of the RCDB, to include:

-  that the RCDB shall coordinate and oversee the work of Project Boards formed for each Project;

-   that the RCDB shall oversee and approve terms of reference of the Project Boards;

-   that the RCDB shall report directly to the Portfolio Holder for Economic Growth, Regeneration and Tourism by way of a report by the Corporate Director (Place & Economy); and

(f)    approves that with the robust project management principles being established and delivered against, constitutional Portfolio Holder responsibilities and corporate oversight through the Regeneration Capital Delivery Board, each project can progress without reference back to Cabinet, unless the details of the individual scopes are proposed to be altered or timescales for delivery are at risk of being contrary to the MOU with MHCLG.

Related Meeting

Cabinet - Monday, 17th March, 2025 10.30 am on March 17, 2025

Details

Decision date17 Mar 2025
Effective from25 Mar 2025
Subject to call-inYes