Cabinet Members' Items - Report of the Economic Growth, Regeneration & Tourism Portfolio Holder - A.4 - Sunspot Workspace, Jaywick Sands - Post Project Review

April 11, 2025 Cabinet (Cabinet collective) Key decision Awaiting outcome View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Cabinet endorsed a post-project review of Sunspot Workspace, Jaywick Sands, noting its success and lessons learned. Cabinet agreed to fund additional costs of up to £100,000 by transferring funds within existing HRA Capital Programme or wider HRA revenue budgets.

Full council record

Decision

RESOLVED that Cabinet –

a)       endorses this post project and operational review of the Sunspot, Jaywick Sands, which highlights the success of the workspace since opening in September 2023, the challenges in construction, and the lessons learnt for future regeneration projects; and

b)       in respect of the additional costs of potentially up to £100,000 that have emerged from the project’s final account processes, agrees that this be funded by a transfer within the existing HRA Capital Programme / wider HRA revenue budgets as part of finalising the overall HRA outturn position for 2024/25.

Related Meeting

Cabinet - Friday, 11th April, 2025 10.30 am on April 11, 2025

Details

Decision date11 Apr 2025
Effective from23 Apr 2025
Subject to call-inYes