Capital Programme Update 2025/26 to 2027/28

November 19, 2025 Cabinet (Cabinet collective) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...new capital schemes costing £2.8M were added to the 2025/26 to 2027/28 Capital Programme, and the revised estimates and financing for that programme were approved.

Full council record
Content

Recommended to Council:
1. 
That the
new capital schemes with a total cost of £2.8M, as shown in
Annex 2 to the report, be added to the 2025/26 to 2027/28 Capital
Programme.
2. 
That the
revised estimates and financing for the 2025/26 to 2027/28 Capital
Programme, as shown in Annex 1 to the report, be
approved.

Related Meeting

Cabinet - Wednesday 19 November 2025 5.30 pm on November 19, 2025

Supporting Documents

Capital Programme Update - Annex 1.pdf
Capital Programme Update - Report.pdf
Capital Programme Update - Annex 2.pdf

Details

OutcomeRecommendations Approved
Decision date19 Nov 2025
Subject to call-inYes