Temporary Accommodation Conversions - Main Works Budgets

September 8, 2026 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Cabinet of Waltham Forest approved a revised gross capital budget of £18,084,330 for temporary accommodation conversions on 08 September 2026. The Cabinet also approved a two-package, single-stage Design and Build procurement strategy, delegating contract award to the Strategic Director of Place. This includes approving the main capital works budgets for the conversion of Rowan House, 130 Trumpington Road, Cedar Wood House, and 90 Crownfield Road.

Full council record

Purpose

Cabinet is recommended to approve the main capital works budgets for the conversion of four vacant council assets for temporary accomodation (Rowan House, 130 Trumpington Road, Cedar Wood House and 90 Crownfield Road)

Decision

Cabinet:

(1)             noted the progress made in developing the four temporary accommodation conversion schemes;

(2)             approved a revised gross capital budget of up to £18,084,330 for the four schemes, noting that the net Council funding requirement after secured grant is £17,597,879 and is expected to be met from General Fund borrowing;

(3)             noted that the revised gross capital budget is £2,723,330, or 17.7%, above the total budget of £15,361,000 approved to date. This comprises £584,000 previously approved by CSAMG and £14,777,000 approved by Cabinet in February 2026. The earlier approvals were based on early-stage estimates and limited site information;

(4)             noted that the full financial case is built on temporary accommodation homes replacing higher-cost external temporary accommodation and the associated General Fund expenditure reducing by c. £800k p.a.;

(5)             approved the proposed two-package, single-stage Design and Build procurement strategy and delegate contract award to the Strategic Director of Place, in consultation with the Strategic Director of Resources and the Director of Governance & Law, subject to tender returns remaining within the approved scheme budgets, the financial appraisal being refreshed, and the resulting General Fund revenue requirement and grant compliance being confirmed before award.

§  Package 1: Rowan House and 130 Trumpington Road

§  Package 2: Cedar Wood House and 90 Crownfield Road

Options & Alternatives Considered

Do nothing - the council could consider not progressing with these redevelopment opportunities.

a)    much-needed higher quality temporary homes within the borough not being delivered

b)    the council paying for more costly forms of temporary accommodation, often in the private rented sector and outside of the borough.

c)    the four council buildings remaining vacant and continuing to cost the council to maintain and manage them.

Alternative delivery method - the council could dispose of the four sites on the open market or look to deliver them with a development partner. However, for both options, it would be unlikely any temporary accommodation would be delivered on the sites. These routes would not align with the council’s Asset Transformation Strategy, which aims to maximise use of the council’s existing estate to deliver positive outcomes for Waltham Forest residents. The development partner option would need to return a profit of between 18% and 20% on Gross Development Value (GDV). This approach would not be viable as there is no profit within the scheme appraisals.

Related Meeting

Cabinet - Tuesday, 8 September 2026 - 2.00 pm on September 8, 2026

Supporting Documents

Appendix 2 RAR SPD Consultation Report.pdf
Appointments of Strategic Director Stronger Communities and Corporate Director Community Safety and .pdf
Residential Alterations and Retrofit SPD Cabinet Report_ June 26.pdf
Appendix 3 Residential Alterations and Retrofit SPD EqIA.pdf
Appendix 4 Sustainability Appraisal.pdf
878062931775568455__-__Site-location-plan-new.pdf
existing-proposed-elevations.pdf
LocationPlan.pdf
59750351770982746__-__P106-PROPOSED-BLOCK-PLAN.pdf
P104-PHTOMONTAGES.pdf
4.1 - 252999 update report FINal.pdf
1.079.200_External Elevations_REV_A.pdf
1.079.300_Section_REV_A.pdf
1_079_002-Site-Plan.pdf
1_079_012-Existing-Second-Floor-Plan-REV-A.pdf
1_079_020-Existing-Elevations.pdf
1_079_030-Existing-Section.pdf
1_079_102_Ground Floor Plan_REV_B.pdf
1_079_103-First-Floor-Plan-REV-A.pdf
1_079_104-Second-Floor-Plan-REV-A.pdf
1_079_105-Third-Floor-Plan-REV-A.pdf
079_260427_DAS_REV_A.pdf
Cabinet Report - Housing Repairs Service Procurement Strategy.pdf
Appendix 2 - Repairs Service Demand and Expenditure Summary.pdf
Appendix 5 - Risk Analysis and Mitigation.pdf
260799 - 6 Croft House.pdf
Non Cabinet Report - Endris.pdf
Appendix C.pdf
Appendix D.pdf
Appendix E.pdf
Supporting information - Francis Keegan.pdf
260651 - 817 - 823 Forest Road.pdf
FOR001-FAR-DR-A-102.pdf
FOR001-FAR-DR-A-104.pdf
FOR001-FAR-DR-A-105.pdf
FOR001-FAR-DR-A-106.pdf
FOR001-FAR-DR-A-107.pdf
FOR001-FAR-DR-A-108.pdf
FOR001-FAR-DR-A-110.pdf
FOR001-FAR-DR-A-111.pdf
FOR001-FAR-DR-A-112.pdf
FOR001-FAR-DR-A-113.pdf
FOR001-FAR-DR-A-114.pdf
FOR001-FAR-DR-A-115.pdf
FOR001-FAR-DR-A-116.pdf
FOR001-FAR-DR-A-117.pdf
FOR001-FAR-DR-A-118.pdf
FOR001-FAR-DR-A-119.pdf
FOR001-FAR-DR-A-120.pdf
FOR001-FAR-DR-A-121.pdf
Non Cabinet Report - Mez Lounge.pdf
Appendix A.pdf
Appendix B.pdf
Appendix C.pdf
Appendix D.pdf
Appendix E.pdf
Acoustic Report - Mez Lounge.pdf
252999 - 41 Orford Rd.pdf
748969101779894730__-__P101-EXISTING-ELEVATIONS.pdf
P103-PROPOSED ELEVATIONS.pdf
P105-SITE LOCATION PLAN.pdf
EVI-006 Rev P2 -Existing Original and As Built N Elevations.pdf
119605-EVO-XX-00-D-A-1300-Ground Floor Demolition Plan-P01.pdf
119605-EVO-XX-00-D-A-1400-Proposed Ground Floor GA Plan-P01.pdf
119605-EVO-XX-00-D-A-7100-Proposed Ground Floor Furniture Layouts-P01.pdf
119605-EVO-XX-01-D-A-1201-Existing First Floor GA Plan-P01.pdf
119605-EVO-XX-03-D-A-1203-Existing Roof Plan-P01.pdf
Appendix A.pdf
Appendix F.pdf
P102-PROPOSED PLANS.pdf
260141 - 176 Wood Street.pdf
1_079_011-Existing-First-Floor-Plan-REV-A.pdf
2655-WWA-ZZ-ZZ-L-D-0100-Landscape-Masterplan.pdf
2655-WWA-ZZ-ZZ-L-D-0101-Bin-Store-Locations-and-Access.pdf
119605-EVO-XX-00-D-A-1200-Existing Ground Floor GA Plan-P01.pdf
119605-EVO-XX-01-D-A-1301-First Floor Demolition Plan-P01.pdf
119605-EVO-XX-01-D-A-1401-Proposed First Floor GA Plan-P01.pdf
119605-EVO-XX-ZZ-D-A-1260-Existing Elevations-P01.pdf
119605-EVO-XX-ZZ-D-A-1500-Proposed Elevations-P01.pdf
119605-EVO-ZZ-XX-D-A-1100-Site Location Plan-P01.pdf
119605-EVO-ZZ-XX-D-A-1120-Proposed-Site-Plan-P03.pdf
Housing Strategy Delivery Update - Cabinet report.pdf
Appendix 1 - Housing Strategy 2024-2029.pdf
Appendix 2 - Housing Strategy delivery Update Summary.pdf
Appendix 3 - Housing Strategy Delivery Tracker.pdf
Appendix 4 - Housing Strategy Performance Data 2025-26.pdf
EVO-XX-XX-D-A-0210 - Existing Elevations Showing Proposed Demolition P1.pdf
260337 - 118 Vansittart Road Report.pdf
622586021772019010__-__PH-118VR-03.pdf
782714501772019022__-__PH-118VR-02.pdf
261690 -130 Trumpington Report.pdf
2655-WWA-ZZ-ZZ-L-D-0101-Bin-Store-Locations-and-Access.pdf
2655-WWA-ZZ-ZZ-L-D-0102-Bin-Storage-Locations-and-Access 2.pdf
119604-XXX-XX-XX-DR-A-0810-Proposed-Site-Plan-P01 1.pdf
119604-XXX-XX-XX-DR-A-0811-Proposed-Site-Elevations 2.pdf
EVO-XX-XX-D-A-0010 - Location Plan p1.pdf
EVO-XX-XX-D-A-0100 - Existing Site Plan p1.pdf
EVO-XX-XX-D-A-0110 - Existing Elevations p1.pdf
EVO-XX-XX-D-A-0120 - Existing Roof Plan p1.pdf
EVO-XX-XX-D-A-0200 - Ground Floor Demolition Plan p1.pdf
EVO-XX-XX-D-A-0290 - Proposed Site Plan p1.pdf
EVO-XX-XX-D-A-0600 - Proposed Elevations p1.pdf
EVO-XX-XX-D-A-1500 - Proposed Sections p1.pdf
EVO-XX-XX-D-A-7000 - GA Plan with Furniture p1.pdf
Temporary Accommodation Conversions - Cabinet Report.pdf
Appendix 1 - Equalities Screening.pdf
2655-WWA-ZZ-ZZ-L-D-0101-Landscape Masterplan.pdf
1_079_001-Location-Plan.pdf
1_079_010-Existing-Ground-Floor-Plan-REV-A.pdf
1_079_013-Existing-Roof-Plan.pdf
1_079_100-Site-Plan.pdf
Appendix 1 - Local Elections 2026 - Results.pdf
Returning Officer 26-27.pdf
1_079_106-Fourth-Floor-Plan-REV-A.pdf
1_079_107-Roof-Plan.pdf
261174 - 43 Pretoria Avenue Report.pdf
Appendix 1 - Contractor Performance Summary.pdf
Appendix 3 - Options Analysis Procurement Strategy 14.5.2026.pdf
0647_P100_Block plan.pdf
0647_Existing drawings 2.pdf
LocationPlan.pdf
Fire Statement - 43 Pretoria Ave.pdf
Minutes of Previous Meeting.pdf
0647_Proposed planning drawings 1.pdf
Members Allowances Scheme 2026-27.pdf
Appendix 1 - Part 10 - Councillors Allowances Scheme 2026-27.pdf
Appendix 6 - EA Screener.pdf
Appendix 4 - Procurement Process and Programme.pdf
LocationPlan 3.pdf
Appendix B.pdf
260713 - 21 East View.pdf
EVI-002 Rev P1 -Existing Site Plan including Roof Plan.pdf
EVI-005 Rev P2 -Existing Original and As Built Roof Plan.pdf
EVI-003 Rev P1 -Proposed Site Plan including Roof Plan.pdf
EVI-004 Rev P2 -Existing Original and As Built Ground Flr Plan.pdf
EVI-007 Rev P2 -Existing Original and As Built E and W Elevations.pdf
EVI-008 Rev P2 -Existing Original and As Built S Elevations.pdf
EVI-009 Rev P1 -Existing Original and As Built Sections.pdf
FOR001-FAR-DR-A-103.pdf
FOR001-FAR-DR-A-101.pdf
119605-EVO-ZZ-XX-D-A-1102-Existing Site Plan Showing Demolition-P01.pdf
261691 - Rowan House 1 Cecil Road Report.pdf
119605-EVO-XX-03-D-A-1402-Proposed Roof Plan-P01.pdf
119605-EVO-ZZ-XX-D-A-1101-Existing Site Plan-P01.pdf
119605-EVO-XX-01-D-A-7101-Proposed First Floor Furniture Layouts-P01.pdf
119605-EVO-XX-ZZ-D-A-1360-Existing Elevations Showing Proposed Demolition-P01.pdf
119605-EVO-ZZ-XX-D-A-1121-Accessible-Space-Site-Entry-Route.pdf
119605-EVO-ZZ-XX-D-A-1501-Proposed-Site-Elevations-P02.pdf
7417857111787159329__-__PH-118VR-01-Rev-A.pdf
EVO-XX-XX-D-A-0150 - Existing Sections p1.pdf
EVO-XX-XX-D-A-0300 - Proposed Ground Floor GA Plan p1.pdf
EVO-XX-XX-D-A-1800 - Proposed Roof Plan p1.pdf

Details

OutcomeRecommendations Approved
Decision date8 Sep 2026
Lead officerSavina Skordili