Additions to the Education Capital Programme 2024/25
April 10, 2025 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve additions to the Education Capital Programme 2024/25, including establishing specialist resourced provisions at Glendale Infant School and Nursery Hill Primary School in Nuneaton, and approving capital works at Nicholas Chamberlaine School, Bilton CofE Junior School, Temple Herdewyke Primary School, and Warton Nethersole CofE Primary School, funded through various allocations.
Full council record
Purpose
Additions of schemes at various schools across Warwickshire including the establishment of specialist resourced provisions.
Decision
Resolved
That Cabinet
1) Approves the establishment of specialist resourced provision at Glendale Infant School, Nuneaton and approves the addition to the capital programme of £0.050 million, funded from the High Needs Provision Capital Allocation, to deliver the prescribed alterations;
2) Approves the establishment of specialist resourced provision at Nursery Hill Primary School, Nuneaton and approves the addition to the capital programme of £0.096 million, funded from the High Needs Provision Capital Allocation, to deliver the prescribed alterations;
3) Approves the addition to the capital programme of £0.127 million to deliver the capital works at Nicholas Chamberlaine School, Bedworth funded from the High Needs Provision Capital Allocation;
4) Approves the addition of £1.105 million to the capital programme to deliver the scheme at Bilton CofE Junior School, Rugby. This will be funded by developer contributions;
5) Approves the addition of £0.253 million to the capital programme to deliver the scheme at Temple Herdewyke Primary School, Temple Herdewyke. This will be funded by developer contributions;
6) Approves the addition to the capital programme of £0.691 million to the capital programme to continue to deliver the scheme at Warton Nethersole CofE Primary School, Warton. This will be funded by developer contributions and Basic Need Funding; and
7) In relation to the schemes covered in this Report, authorises the Executive Director for Children and Young People, in consultation with the Portfolio Holder for Finance and Property, to invite tenders and enter into the appropriate contracts or (where the scheme is school led) to make the necessary funding arrangements for these schemes on terms and conditions considered acceptable to the Executive Director for Resources.
Related Meeting
Cabinet - Thursday 10 April 2025 1.45 pm on April 10, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 10 Apr 2025 |