Establishment of Specialist Resourced Provision at four Infant / Primary Schools
June 15, 2023 Cabinet (Cabinet collective) Key decision Approved View on council websiteFull council record
Purpose
Statutory approval for the establishment of
Specialist Resourced Provision at Goodyers End Primary School,
Abbey CofE Infant School, and St Andrews Benn CofE Primary
School
Decision
Resolved
That Cabinet:
1)
Approves the establishment of
specialist resourced provision at the four schools set out in
Section 3 and approves the following additions to the capital
programme to deliver the prescribed alterations
required:
a) For Abbey CofE Infant School, an
addition to the capital programme of £0.048 million to be
funded from the High Needs Capital Grant;
b) For Goodyers End Primary School, an addition of
£0.089 million to the capital programme to be funded from the
Special Provision Fund and the High Needs Capital Grant;
c) For St Andrew’s Benn CE
Primary School, an addition of £0.028 million to the capital
programme to be funded from Developer Contributions;
d) For St Matthew’s Bloxam CE Primary School, an addition of
£0.026 million to be funded from Developer Contributions;
and
2)
Authorises the Strategic Director for
People to invite tenders and to enter into any agreements necessary
to deliver the provisions approved on terms and conditions
considered acceptable to the Strategic Director for
Resources.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 15 Jun 2023 |