69 High Street Godalming

October 14, 2025 Executive (Other) Key decision Awaiting outcome View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to recommend to full Council the approval of an additional budget of £540,000 and, subject to that approval, to approve the appointment of ETEC Group Limited as contractor for the demolition and refurbishment of the commercial unit at 69 High Street, Godalming, delegating contract authority to the Strategic Director of Economy, Planning and Place.

Full council record
Purpose

Approval to enter into works contract for the
demolition and build of the first phase development.

Content

RESOLVED that:
 

1.   
Subject to the amendment of the report to Council to include the
additional information requested by the Overview and Scrutiny
Committee and the inclusion of ‘Option 6’ to delay the
Council’s decision until its meeting in December, The content
of the report be endorsed by the Executive and it be recommended to
Council at its meeting on 22nd October 2025:
a.   
That full Council approves the required additional budget of
£540,000 to progress the project at 69 High Street,
Godalming, to be funded from the Revenue Account Reserve (General
Fund working balance).
 
2.   
That, strictly subject to full Council approving the required
additional budget, the Executive resolves to:
a.   
Approve the appointment of ETEC Group Limited as contractor to
complete all works associated with the demolition of the building
at 69 High Street, Godalming and its refurbishment for the
commercial unit only.
b.   
Delegates to the Strategic Director of Economy, Planning and Place
the authority to enter into the contract with ETEC Group Limited,
together with such other contracts and legal agreements connected
with the 69 High Street project as may be necessary, in compliance
with Procurement Procedure Rules, the Council’s Constitution
and within the approved budget (as revised under recommendation
2.1.1 of the report).
 

Related Meeting

Executive - Tuesday, 14th October, 2025 7.00 pm on October 14, 2025

Supporting Documents

69 High Street Godalming.pdf
Portfolio Holder Response to OS Recommendations.pdf

Details

OutcomeFor Determination
Decision date14 Oct 2025