Sports England Funding SPSF Phase 2 for Carterton Leisure Centre Solar PV

March 21, 2025 Chief Executive & Head of Paid Service - Giles Hughes (Officer) Key decision Approved View on council website
Full council record

Purpose

To consider the acceptance of
funding offer from Sports England in the amount of
£350k.

Decision

The Chief Executive,
following consultation with the Chair of the Overview and Scrutiny
Committee, Executive Member for Finance and Executive Member for
Leisure and Major Projects, resolved to:

Approve the
funding application to Sports England.

 

Reasons for the decision

The Council has been approached by Sports
England who have offered to fund its 2nd claim, that was circa
£350,000 from the Swimming Pool Funding Scheme, which was
previously rejected due to oversubscription of the
scheme. 

Alternative options considered

Alternative option: The Council may wish not
to accept the SPSF offered by Sport England due to tight timescales
associated with the project. This is not the preferred option.

Supporting Documents

Sport England Funding for PV on Carterton - 20.03.25.pdf

Details

OutcomeRecommendations approved
Decision date21 Mar 2025