Luxborough Final Account
December 19, 2024 Cabinet Member for Regeneration and Renters (Cabinet member) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve the Luxborough final account with Wates Construction Limited at £11.25m, an increase of £2.65m, and to authorize the additional £2.65m spend and a £1.15m drawdown from the General Fund Central Contingency, noting that £1.5m was already budgeted.
Full council record
Purpose
Requesting additional budget for the
Luxborough final account.
Decision
The Cabinet Member for Regeneration and
Renters has approved:
The final account?agreed between WCC
and Wates Construction Limited of £11.25m, an increase of
£2.65m (31% increase) on the approved construction costs of
£8.6m in 2021/22.
The additional?£2.65m spend on
the construction contract subject to being endorsed in line with
the Council’s Procurement Code and Financial
Regulations.
A drawdown from the General Fund
Central Contingency within the approved capital programme to fund
the balance of £1.15m in 24/25.
To note of the £2.65m
variance, £1.5m has already been budgeted for within the
23/24 Capital Strategy approved by Full Council in March
2024.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 19 Dec 2024 |
| Subject to call-in | Yes |