SuDS Delivery Programme 25/26

July 2, 2025 Cabinet Member for Planning and Economic Development (Cabinet member) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve the proposed approach to the next delivery phase of the SuDS Programme, approve the drawdown of £1,645,000 from the capital budget, and delegate authority to the Executive Director of Environment & Communities to approve final allocations of these funds to individual projects, in consultation with Finance.

Full council record

Purpose

The Cabinet Member for Planning and Economic
Development will consider the Sustainable Drainage Systems
(SuDS) delivery programme for the
2025/26 financial year.

Decision

Summary of Decision: The Cabinet Member
for Planning and Economic Development has taken the decision to
approves the proposed approach to the next delivery phase of the
SuDS Programme and approve the drawdown of £1,645,000 from
the capital budget; and has delegated authority to the Executive
Director of Environment & Communities to approve final
allocations of these funds to individual projects, in consultation
with Finance
 
Reason for Decision: The council has
approved £3.7 million for SuDS delivery through the Capital
Programme Strategic Review?(CPSR) between 24/25 to 27/28.
Expenditure so far has focused on developing a strategy for SuDS
delivery, agreeing standard design processes and incubating SuDS
delivery within existing public realm schemes. The next phase of
this programme will see the delivery of standalone SuDS projects
which strategically target locations based on hydrological,
environmental and socio-economic priority, in addition to
continuing the delivery of SuDS as part of ongoing public realm
improvement works.

Supporting Documents

Appendix B - SuDS Masterplan TN - part one.pdf
CMR - SuDS Delivery Programme.pdf
Appendix B - SuDS Masterplan TN - part two.pdf
Appendix A - SuDS Masterplan_North Paddington_Technical Note.pdf

Details

OutcomeRecommendations Approved
Decision date2 Jul 2025
Subject to call-inYes